Record the gateway decisions of MIL-001 and MIL-002 #17

Merged
Tirsvad merged 2 commits from record-gateway-decisions into main 2026-10-07 18:28:13 +02:00
2 Commits
Author SHA1 Message Date
Tirsvad e6988d5648 Resolve pending commit link
Replace `pending` in the Version History of PP-001 with a link to the commit
that introduced the row.
2026-10-08 00:27:20 +08:00
Tirsvad a6b17d30bc Record the Go decisions of MIL-001 and MIL-002 in the Project Plan
Add a Gateway Decisions section to PP-001: S01 decided Go on both gateways on
2026-10-08, ahead of the planned 2026-10-09 and 2026-10-14, because every Go
criterion was already met. Each row names the criteria, the review record
(RC-005, RC-006) and the merged pull request (#14, #16).

Close the reference-image open issue, which has been resolved since S01
supplied the image on 2026-10-07. The two open decisions on RC-006 (the display
requirement of the tests, the pale palette colours) did not block either gate.
2026-10-08 00:27:13 +08:00