Add RC-001 to RC-005 for the Business Case, Stakeholder Analysis and
MIL-001 to MIL-003, checked against their QC checklists, and a
traceability matrix. The reviews found a missing duration constraint in
the Business Case; BC-001 v2 adds it, and SA-001 v2 records the
sign-off. Register RC and TM in the artifact registry.
Plan MIL-004 (review the source against QC-PY-001, add a CI workflow)
as Proposed, with Business Case objective 6, a Project Plan gateway
row and a matrix entry. The milestone is not yet synced to the git host.
No issue closed: planning and review documents only, no code changed.
Draft and accept the Business Case, Stakeholder Analysis (S01-S03) and
Project Plan for the Day 15 coffee machine assignment. Add three
milestones with 17 tasks, synced to the git host as Milestones 40-42
and Issues #1-#17. Register PP and MIL in the artifact registry and set
the PO language to en.
No issue closed: planning only, no code changed.