Tirsvad 8ef00aafaa Add SQA review records and plan MIL-004 Code Review and CI
Add RC-001 to RC-005 for the Business Case, Stakeholder Analysis and
MIL-001 to MIL-003, checked against their QC checklists, and a
traceability matrix. The reviews found a missing duration constraint in
the Business Case; BC-001 v2 adds it, and SA-001 v2 records the
sign-off. Register RC and TM in the artifact registry.

Plan MIL-004 (review the source against QC-PY-001, add a CI workflow)
as Proposed, with Business Case objective 6, a Project Plan gateway
row and a matrix entry. The milestone is not yet synced to the git host.

No issue closed: planning and review documents only, no code changed.
2026-10-06 20:42:51 +08:00

4.7 KiB
Raw Blame History

Business Case

Metadata

Key Value
ID BC-001
CrossReference SA-001

Version History

Date Status Author Reviewer Change Commit
2026-10-06 Accepted Jens Tirsvad Nielsen S01 Added duration constraint (RC-001 action) pending
2026-10-06 Proposed Jens Tirsvad Nielsen S01 Added objective 6 and scope for code review and CI pending

Executive Summary

Build a console coffee machine in Python as the Day 15 assignment of Udemy's "100 Days of Code: The Complete Python Pro Bootcamp". The program serves espresso, latte and cappuccino, accepts US coins, tracks water, milk and coffee and prints a report on request. It is published as a readable, runnable reference for other course participants and as a portfolio piece.

Methodological and Standards Foundation

Planning follows the SQA/QC framework mounted at framework/ (plan first, then code). Quality is described with ISO/IEC 25010:2023 characteristics. Code uses the coding-conventions skill and Doxygen comments.

Problem Statement

The assignment specification is long and detail-heavy (resources, coins, refunds, change). Solutions shared by participants vary widely in structure and readability, and a single main.py script is hard to test.

Business Opportunity

A small, well-structured and tested solution is a clear example for other participants and for viewers browsing the repository.

Objectives

  1. Implement the full assignment behaviour: report, off, drink selection, resource check, coin processing, change, profit.
  2. Keep the assignment's function names so participants can compare solutions.
  3. Cover the behaviour with automated pytest tests.
  4. Document how to set up a local .venv and run the program and tests.
  5. Publish the repository with a description, topics and README.
  6. Review the source code against the Python quality checklist and run the tests and code checks automatically on every push.

Scope

In Scope

  • Console program under src/ with a constants.py for menu, coins and starting resources.
  • pytest tests under tests/.
  • pyproject.toml, Python .gitignore, Doxyfile, README.md.
  • Project documents under docs/.
  • Repository description and topics on the git host.
  • A review record for the source code and a CI workflow (MIL-004).

Out of Scope

  • Graphical or web interface.
  • Payment other than the four US coins.
  • Persistence of resources or profit between runs.
  • Runtime dependencies.

Expected Benefits

Tangible Benefits

  • Completed Day 15 assignment.
  • Runnable code with tests and setup instructions.

Intangible Benefits

  • Practice with planning, testing and Python project layout.
  • A reusable template for later course projects.

Strategic Alignment

Supports the learner's goal of finishing the 100 Days of Code course with professional project hygiene, and the goal of sharing readable solutions.

Success Criteria

# Criterion Target Measure
1 Assignment behaviours implemented 100% of listed behaviours Manual run against the specification
2 Tests pass All pytest tests green python -m pytest
3 Runtime dependencies 0 pyproject.toml dependencies is empty
4 Setup documented A new reader can run program and tests from README README walkthrough
5 Repository metadata Description and at least 3 topics set Repository page

Risks

Risk Impact Mitigation
Floating-point rounding in coin totals Wrong change or refund Compute money in cents (integers) internally
Token in .env leaks Account compromise .env is gitignored, never imported or tested by the project
Scope creep beyond the assignment Delay Out of Scope list above

Assumptions

  • Python 3.13 or newer is installed.
  • The git host repository already exists and is reachable.

Constraints

  • Python greater than 3.13 as requested, venv for environments, pytest for tests.
  • Constants live in constants.py.
  • Source files use Doxygen comments.
  • Nothing is committed or pushed unless the user asks.
  • Duration: one week, 2026-10-05 to 2026-10-12.

Cost–Benefit Assessment

Costs Benefits
A few hours of the learner's time Finished, tested, shareable assignment (qualitative; no money involved)

Stakeholders

Stakeholder ID (SA) Interest in this project
S01 Completes the assignment and owns the plan, code and review
S02 Reads and runs the code, compares solutions
S03 Browses the repository for ideas

Recommendation

Proceed — the scope is small, well specified and delivers a reusable example.