Review Record: PP-001 against QC-PP-001

Metadata

Key Value
ID RC-003
CrossReference PP-001, QC-PP-001, QC-LANG-001

Version History

Date Status Author Reviewer Change Commit

Artifact Under Review

  • Instance reviewed: PP-001
  • Checklist used: QC-PP-001 and QC-LANG-001
  • Scope: full review
  • Language and domain: en / it
  • Language reviewer: none (the stand-in reads English and knows the IT domain)
  • Mode: autonomous, not independent (Stand-in for S01)

Checklist Results

# Criterion Status Evidence/Notes
1 The plan states its start date, end date and the constraint it must fit Pass Planning Assumptions give the start and end dates (2026-11-21 to 2026-11-28); the Business Case sets no external deadline, so the plan keeps to its one-week target.
2 Every milestone or gateway is listed once with its document, decision date and owner Pass The Gateway Schedule lists MIL-001, MIL-002 and MIL-003 once each with document, decision date and owner; all three documents exist and no gateway is missing from the plan.
3 Every decision date lies inside the plan's window and is consistent with the dates in the linked MIL-* document Pass Every decision date lies in its window and equals the Target Date of its milestone (2026-11-22, 2026-11-26 and 2026-11-28).
4 Every in-scope item of the Business Case is delivered at a named gateway (scope coverage) Pass Scope Coverage maps every In Scope item of BC-001 to a gateway; the screenshot item maps to MIL-002 and MIL-003.
5 Dependencies between gateways are stated, acyclic and consistent with the schedule order Pass The chain MIL-001 to MIL-002 to MIL-003 is acyclic and in schedule order, as the Dependencies section says.
6 The plan states what happens to later gateways and to the end date when a gateway is No-Go Pass Dependencies state that a No-Go on a gateway returns it to S01, moves the later gateway and the end date and that S01 decides the new date; each gateway needs its predecessor.
7 Owners, reviewers and escalation roles use Stakeholder Analysis IDs and match the governance RACI Pass Owner S01 and reviewer S01 (or the stand-in for S01) are stakeholder IDs of SA-001; no governance document exists, so there is no RACI to contradict.
8 Planning assumptions are listed with their source, and a changed baseline is recorded with its reason Pass Each planning assumption names its source or is a decision of S01; no baseline has been changed yet, so there is no move to record.
9 Plan risks are listed with impact and a mitigation, and trace to Business Case risks where they come from there Pass Plan Risks give impact and mitigation for each of the two risks; the screenshot risk traces to the screenshot risk of BC-001.
10 Open issues are listed, and none contradicts a statement elsewhere in the plan Pass Open Issues lists two points; none contradicts the rest of the plan.
11 Each gateway's main deliverable is stated and matches the deliverable of its MIL-* document Pass The main deliverable of each gateway is the first-named deliverable of its milestone; for MIL-002 and MIL-003 it names the same items as their Deliverable sections.
12 Gateways that deliver user stories name them, and those that do not say why Pass The Stories column says none for both gateways; the Open Issues explain that no use case or user story is modelled.
13 The schedule view (table, Gantt) and the dependency view agree with each other Pass The Gantt bars use the dates of the schedule table; the dependency line agrees with the order.
14 Each gateway is linked to its issue-tracker milestone, or marked as not yet synced Pass All three gateways are marked not yet synced; the links follow after the milestones are published.
15 The plan is a singleton: one Project Plan per project, changes recorded in Version History Pass PP-001 is the only Project Plan; its Version History records each change in its own row and only the latest row is Accepted.

Language and Domain Results

# Criterion Status Evidence/Notes
1 The Metadata table has a Language row and a Domain row, and neither is a placeholder Pass The Metadata table has `Language
2 Language is a BCP 47 code and Domain is a value from the registry's domain list Pass en is a BCP 47 code and it is a row of the domain list of docs/artifact-registry.md.
3 The content (prose and table cells) is written in the stated language Pass The prose and the table cells are English; only file names, commands and IDs are code.
4 The register matches the one the registry gives for the artifact type Pass The registry gives the register IT Executive English for this type; the text is short, plain and written for that reader.
5 Domain terms are the PO terms of the domain's dictionary, with no synonyms Pass No dictionary (DICT) exists in this project. The text uses the terms game, ship, alien, barrier, score, window and screenshot in one meaning each, with no synonym.
6 Metadata keys, section headings, IDs and statuses are in English Pass Metadata keys, section headings, IDs and statuses are the framework's English ones.
7 No translated twin (<name>.<language>.md) exists beside the document Pass No file <name>.<language>.md exists beside the document.
8 A change of language or domain since the previous accepted version has a Version History row and was reviewed again Pass The Domain row changed from it to it in this version (the language en is unchanged). The Version History row records the change and this review covers it.
9 A reviewer competent in the domain, and in the language, has confirmed that the domain terms are used correctly Pass The stand-in reads English and knows the IT domain and checked the terms; the check is autonomous and not independent.
10 Abbreviations are spelled out on first use, in the stated language Pass Abbreviations are spelled out where they are first used (SQA, QC, CI, FURPS+) or are established names (README, API, PEP, Tk).

Overall Verdict

Go — every Mandatory criterion of QC-PP-001 and QC-LANG-001 passes after the edits of this change; the document is Accepted. Review of the whole document after the edits of this change.

Action Items

Action Owner Due
No open action S01 2026-11-22