Files
095-assignment-space-invaders/docs/project-plan.md
Tirsvad 40f1500001
TirSystem/git-workflows: CI / secret-scan (push) Skipped
TirSystem/git-workflows: CI / validate (push) Skipped
TirSystem/git-workflows: CI / opengrep (push) Skipped
TirSystem/git-workflows: CI / release-check (push) Skipped
TirSystem/git-workflows: Publish wiki / publish-wiki (push) Skipped
TirSystem/git-workflows: Release / release (push) Skipped
TirSystem/git-workflows: Sync GitHub mirror metadata / sync-metadata (push) Skipped
TirSystem/git-workflows: Publish accepted milestones / publish (push) Skipped
TirSystem/git-workflows: Validate / validate (push) Skipped
TirSystem/git-workflows: CI / secret-scan (pull_request) Successful in 12s
Tests / test (pull_request) Successful in 42s
TirSystem/git-workflows: Release / release (pull_request) Successful in 7s
TirSystem/git-workflows: Validate / validate (pull_request) Successful in 20s
TirSystem/git-workflows: OpenGrep / opengrep (pull_request) Successful in 58s
TirSystem/git-workflows: CI / validate (pull_request) Successful in 18s
TirSystem/git-workflows: CI / release-check (pull_request) Successful in 6s
TirSystem/git-workflows: CI / opengrep (pull_request) Successful in 53s
Resolve the pending commit links
2026-11-21 18:29:48 +08:00

4.2 KiB

Project Plan

Metadata

Key Value
ID PP-001
CrossReference BC-001, SA-001, MIL-001, MIL-002, MIL-003
Language en
Domain it

Version History

Date Status Author Reviewer Change Commit
2026-11-21 Deprecated Jens Tirsvad Nielsen Stand-in for S01 Accepted with a Go (RC-003); reviewed in autonomous mode, not independent 587a239
2026-11-21 Accepted Jens Tirsvad Nielsen Stand-in for S01 Linked the three milestones of the git host in the schedule and updated the open issues; reviewed in autonomous mode, not independent (RC-018) 0449c45

Purpose

Schedules the three gateways of the Space Invaders project within one week, with one branch and one pull request per task so the steps stay traceable.

Planning Assumptions

  • The plan starts 2026-11-21 and ends by 2026-11-28; the Business Case sets no external deadline.
  • Phase length: one to four days; one pull request per task.
  • S01 owns, builds and reviews; review is by S01 or, in autonomous mode, by a stand-in for S01, and the review record says so.
  • Screenshots are taken in a Docker container, never on the host desktop.

Gateway Schedule

Gateway Document Window Decision date Owner Stories Main deliverable Milestone
Project setup MIL-001 2026-11-21 to 2026-11-22 2026-11-22 S01 none Scaffold, README, screenshot harness, repository description and topics milestone-698
Game build MIL-002 2026-11-22 to 2026-11-26 2026-11-26 S01 none Playable, tested game built in nine steps milestone-699
Wiki and screenshots MIL-003 2026-11-26 to 2026-11-28 2026-11-28 S01 none README screenshots and wiki in three languages milestone-700
@startgantt
Project starts 2026-11-21
[Project setup] starts 2026-11-21 and ends 2026-11-22
[Game build] starts 2026-11-22 and ends 2026-11-26
[Wiki and screenshots] starts 2026-11-26 and ends 2026-11-28
[MIL-003 Go/No-Go] happens 2026-11-28
@endgantt

Scope Coverage

Business Case scope item Gateway
pyproject.toml, .gitignore, constants.py, Doxyfile, README, tests set-up MIL-001
Repository description and topics, local scan MIL-001
Game, barriers, game over, score and lives, tests, Doxygen comments MIL-002
Screenshot per build step MIL-002 (taken) and MIL-003 (published)
Wiki in three languages and reflection journal MIL-003

Dependencies

MIL-001 → MIL-002 → MIL-003

Each gateway needs the one before it. A No-Go returns the gateway to S01 and moves the later dates; S01 decides the new date.

Plan Risks

Risk Impact Mitigation
Tk in the Docker image or the virtual display fails No screenshots Build the harness first (MIL-001 task 4); stop and report if no isolated environment works
Translations lag the English text Gateway date slips English is authoritative; translate page by page after it is stable

Open Issues

  • No use case or user story is modelled: the tasks are technical or documentation tasks, so the Stories column says none.
  • The git host published the three milestones after the first merge (milestones 698 to 700); MIL-001 and MIL-002 are finished and their issues are closed, and the milestones are closed when MIL-003 is merged.