Link the five gateways to their milestones on the host
No issue closed: documentation of the synced milestones only.
2026-10-28 14:40:09 +08:00

5.4 KiB

Project Plan

Metadata

Key Value
ID PP-001
CrossReference BC-001, SA-001, MIL-001, MIL-002, MIL-003, MIL-004, MIL-005
Language en
Domain it

Version History

Date Status Author Reviewer Change Commit
2026-10-28 Accepted Jens Tirsvad Nielsen S01 (AI as stand-in, autonomous mode) Initial version dcef5e6

Purpose

Schedule the five gateways that deliver the Day 45 scraping repository. The Business Case sets no deadline, so the plan only fixes the order and a working window per gateway.

Planning Assumptions

  • Week 1 starts 2026-10-28; the plan ends by 2026-11-14 (no hard deadline in BC-001).
  • Phase length: two to four days; each phase is one branch and one pull request.
  • Communication follows SA-001: plan acceptance in chat, one pull request per milestone, run summary at the end.
  • Autonomous mode: S01 accepts this plan once; the AI then runs every gateway and acts as stand-in reviewer, recorded in each RC record.

Gateway Schedule

Gateway Document Window Decision date Owner Stories Main deliverable Milestone
Repository Setup MIL-001 2026-10-28 to 2026-10-30 2026-10-30 S01 none (technical tasks) Repository metadata, configuration, README, CI Milestone 259 (closed)
Parsing HTML MIL-002 2026-10-31 to 2026-11-03 2026-11-03 S01 none (technical tasks) soup_basics module, tests, screenshots Milestone 260 (closed)
Hacker News MIL-003 2026-11-04 to 2026-11-06 2026-11-06 S01 none (technical tasks) hacker_news module, ethics note, screenshots Milestone 261 (closed)
Top 100 Movies MIL-004 2026-11-07 to 2026-11-10 2026-11-10 S01 none (technical tasks) movies module and movies.txt, screenshots Milestone 262 (closed)
Wiki MIL-005 2026-11-11 to 2026-11-14 2026-11-14 S01 none (technical tasks) Wiki in en, da, ms Milestone 263 (closed)
@startgantt
Project starts 2026-10-28
[Repository Setup] starts 2026-10-28 and ends 2026-10-30
[Parsing HTML] starts 2026-10-31 and ends 2026-11-03
[Hacker News] starts 2026-11-04 and ends 2026-11-06
[Top 100 Movies] starts 2026-11-07 and ends 2026-11-10
[Wiki] starts 2026-11-11 and ends 2026-11-14
[MIL-001 Go/No-Go] happens 2026-10-30
[MIL-002 Go/No-Go] happens 2026-11-03
[MIL-003 Go/No-Go] happens 2026-11-06
[MIL-004 Go/No-Go] happens 2026-11-10
[MIL-005 Go/No-Go] happens 2026-11-14
@endgantt

Scope Coverage

Business Case scope item Gateway
pyproject.toml, .gitignore, Doxyfile, constants.py, README skeleton MIL-001
Repository description and topics, workflows MIL-001
Parsing HTML, finding and selecting elements MIL-002
Hacker News scraping and the ethics note MIL-003
100 movies and movies.txt MIL-004
Wiki in en, da, ms and screenshots per step MIL-005 (screenshots are taken in MIL-002 to MIL-004)

Dependencies

MIL-001 → MIL-002 → MIL-003 → MIL-004 → MIL-005

A No-Go on a gateway is fixed and re-reviewed; after three failed rounds the run stops and reports (AGENTS.md). Later dates move by the same amount; S01 decides a move of the end date.

Plan Risks

Risk Impact Mitigation
Target repository name differs from the one named in the request Metadata set on the wrong repository Resolved: S01 chose the origin remote at plan acceptance
Reusable workflow path differs (TirSystem/git-workflows in the template, TirSystem/github-action named in the request) Workflow calls fail Verify the path on the host in MIL-001 before installing
Danish and Malay translation quality Review finds errors Keep sentences short; English is authoritative
Network access to Wayback during the run Fixture cannot be saved Retry once; alternative live Empire URL

Open Issues

  • Target repository: S01 chose the origin remote (Tirsvad-Udemy-100-days-of-code/045-scrape-movies) when accepting the plan; the named Tirsvad-Udemy-100_days_of_code is not used.
  • Wiki publication is a scoped workflow in TirSystem/github-action (no file needed) while the framework template publish-wiki.yml also exists; MIL-001 records which one applies.
  • "Screenshot per lecture step" is planned as rendered terminal output and browser-pane captures, never host desktop capture.