Tirsvad 8ef00aafaa Add SQA review records and plan MIL-004 Code Review and CI
Add RC-001 to RC-005 for the Business Case, Stakeholder Analysis and
MIL-001 to MIL-003, checked against their QC checklists, and a
traceability matrix. The reviews found a missing duration constraint in
the Business Case; BC-001 v2 adds it, and SA-001 v2 records the
sign-off. Register RC and TM in the artifact registry.

Plan MIL-004 (review the source against QC-PY-001, add a CI workflow)
as Proposed, with Business Case objective 6, a Project Plan gateway
row and a matrix entry. The milestone is not yet synced to the git host.

No issue closed: planning and review documents only, no code changed.
2026-10-06 20:42:51 +08:00

3.9 KiB

Project Plan

Metadata

Key Value
ID PP-001
CrossReference BC-001, SA-001, MIL-001, MIL-002, MIL-003, MIL-004

Version History

Date Status Author Reviewer Change Commit
2026-10-05 Accepted Jens Tirsvad Nielsen S01 Initial version c0c3940
2026-10-06 Proposed Jens Tirsvad Nielsen S01 Added MIL-004 Code Review and CI pending

Purpose

Schedule the three phases that take the coffee machine from empty repository to published project, within the short assignment timeline in BC-001.

Planning Assumptions

  • Week 1 starts 2026-10-05; the plan ends by 2026-10-12.
  • Phase length: two to three days; S01 reviews each phase through a pull request (see SA-001).
  • Each phase is one branch and one pull request.

Gateway Schedule

Gateway Document Window Decision date Owner Stories Main deliverable Milestone
Project Setup MIL-001 2026-10-05 to 2026-10-07 2026-10-07 S01 none Skeleton, tooling, README Milestone 40
Coffee Machine Core MIL-002 2026-10-08 to 2026-10-10 2026-10-10 S01 none Working program Milestone 41
Quality and Publication MIL-003 2026-10-11 to 2026-10-12 2026-10-12 S01 none Tests, Doxygen, published repo Milestone 42
Code Review and CI MIL-004 2026-10-07 to 2026-10-12 2026-10-12 S01 none Source review record, CI workflow
@startgantt
Project starts 2026-10-05
[Project Setup] starts 2026-10-05 and ends 2026-10-07
[Coffee Machine Core] starts 2026-10-08 and ends 2026-10-10
[Quality and Publication] starts 2026-10-11 and ends 2026-10-12
[MIL-001 Go/No-Go] happens 2026-10-07
[MIL-002 Go/No-Go] happens 2026-10-10
[MIL-003 Go/No-Go] happens 2026-10-12
[Code Review and CI] starts 2026-10-07 and ends 2026-10-12
[MIL-004 Go/No-Go] happens 2026-10-12
@endgantt

Scope Coverage

Business Case scope item Gateway
Console program with constants.py MIL-002
pytest tests MIL-003
pyproject.toml, .gitignore, Doxyfile, README MIL-001
Project documents Planning, before MIL-001
Repository description and topics MIL-003
Source code review record and CI workflow MIL-004

Dependencies

MIL-001 -> MIL-002 -> MIL-003 -> MIL-004

A No-Go moves all later dates by the same amount.

Plan Risks

Risk Impact Mitigation
The git host has no Actions runner CI cannot run Check the host first; if none, keep the workflow file and document the local commands
README template not supplied README task blocked Ask S01 for the template before the task
Doxygen not installed locally Cannot verify docs Document the install step in README

Open Issues

  • The README template referenced in the request ("template below") was not included.
  • No use cases or user stories are written; tasks are plain technical tasks implementing the assignment specification. S01 can ask for a use case ("Order a drink") if wanted.
  • Python ">3.13" is read as 3.13 or newer (>=3.13).