Project Plan

Metadata

Key Value
ID PP-001
CrossReference BC-001, SA-001, MIL-001, MIL-002, MIL-003, MIL-004

Version History

Date Status Author Reviewer Change Commit
2026-10-04 Proposed Jens Tirsvad Nielsen S01 Initial version ddfe96f

Purpose

Schedule the four phases that deliver the Higher Lower game (BC-001 objectives O1–O5) as a small, tested, documented Python project, with S01 reviewing each phase through its own branch and pull request.

Planning Assumptions

  • Week 1 starts 2026-10-04; the plan ends by 2026-10-14 (the Business Case sets no hard date; this is the author's evening-sized target, see Open Issues).
  • One phase per branch and pull request, each closing its issues.
  • Nothing under src/ or tests/ before the milestone is accepted and the task is a row in it.
  • Only S01 reviews (SA-001).

Gateway Schedule

Gateway Document Window Decision date Owner Stories Main deliverable Milestone
Project setup MIL-001 2026-10-04 – 2026-10-06 2026-10-06 S01 — pyproject, Doxyfile, skeleton, repo metadata
Game logic MIL-002 2026-10-07 – 2026-10-09 2026-10-09 S01 — Data, art, constants, pure functions, tests
Console game MIL-003 2026-10-10 – 2026-10-12 2026-10-12 S01 — Playable game loop with score, tests
Documentation and release MIL-004 2026-10-13 – 2026-10-14 2026-10-14 S01 — README, Doxygen run, review records
@startgantt
Project starts 2026-10-04
[Project setup] starts 2026-10-04 and ends 2026-10-06
[Project setup Go/No-Go] happens 2026-10-06
[Game logic] starts 2026-10-07 and ends 2026-10-09
[Game logic Go/No-Go] happens 2026-10-09
[Console game] starts 2026-10-10 and ends 2026-10-12
[Console game Go/No-Go] happens 2026-10-12
[Documentation and release] starts 2026-10-13 and ends 2026-10-14
[Documentation and release Go/No-Go] happens 2026-10-14
@endgantt

Scope Coverage

Business Case scope item Gateway
src/, tests/, docs/ layout, pyproject.toml, .gitignore, Doxyfile MIL-001
Repository description and topics MIL-001
Assignment data set, logo and vs art MIL-002
Random pair selection, answer checking MIL-002
Console game, score tracking MIL-003
README.md, venv and test instructions MIL-004

Dependencies

MIL-001 → MIL-002 → MIL-003 → MIL-004

A No-Go on any phase moves all later windows by the rework time.

Plan Risks

Risk Impact Mitigation
README template not supplied README task blocked Ask S01 before MIL-004 starts
Host token missing or lacking scope Cannot sync issues or set topics Token read from .env for personal use only; ask S01 if absent
Doxygen not installed locally Cannot verify docs build Treat as a No-Go note; install or review comments manually

Open Issues

  • README template: the brief says "using the template below" but none was included. Needed before MIL-004.
  • Python version: "greater than 3.13" is planned as >=3.13; confirm if strictly 3.14+ is meant.
  • Target dates are proposed, not stated in the brief; confirm.
  • The brief links the organisation; the origin remote is the repository 014-higher_lower within it, which is what will be synced.