Add inception baseline and milestone plan for Higher Lower #22

Merged
Tirsvad merged 3 commits from g1-inception-baseline into main 2026-10-04 17:24:34 +02:00
Owner

Summary

Planning baseline for the Higher Lower game (Udemy 100 Days of Code, day 14). No code under src/ or tests/.

  • Business Case (BC-001), Stakeholder Analysis (SA-001), Project Plan (PP-001)
  • Four milestones with Go/No-Go criteria and task tables: MIL-001 Project setup, MIL-002 Game logic, MIL-003 Console game, MIL-004 Documentation and release
  • Milestones 36-39 and issues #1-#20 synced to the host; the Project Plan links the milestones
  • Repository description and topics set via the API
  • BC-001, SA-001, PP-001 and MIL-001 reviewed (RC-001 to RC-004, all Go) and Accepted; MIL-002 to MIL-004 stay Proposed
  • Traceability Matrix (TM-001) added

Open items

  • README template not supplied yet (blocks #17)
  • requires-python planned as >=3.13; confirm if 3.14+ is meant
  • Target dates (2026-10-06 to 2026-10-14) are proposed
  • UC-001 "Play a game" is referenced by #13 and not yet created
  • Author and reviewer are both S01 (single participant); noted in each review record

Closes #5

## Summary Planning baseline for the Higher Lower game (Udemy 100 Days of Code, day 14). No code under `src/` or `tests/`. - Business Case (BC-001), Stakeholder Analysis (SA-001), Project Plan (PP-001) - Four milestones with Go/No-Go criteria and task tables: MIL-001 Project setup, MIL-002 Game logic, MIL-003 Console game, MIL-004 Documentation and release - Milestones 36-39 and issues #1-#20 synced to the host; the Project Plan links the milestones - Repository description and topics set via the API - BC-001, SA-001, PP-001 and MIL-001 reviewed (RC-001 to RC-004, all Go) and Accepted; MIL-002 to MIL-004 stay Proposed - Traceability Matrix (TM-001) added ## Open items - README template not supplied yet (blocks #17) - `requires-python` planned as `>=3.13`; confirm if 3.14+ is meant - Target dates (2026-10-06 to 2026-10-14) are proposed - UC-001 "Play a game" is referenced by #13 and not yet created - Author and reviewer are both S01 (single participant); noted in each review record Closes #5
Tirsvad added 2 commits 2026-10-04 17:23:56 +02:00
Review BC-001, SA-001, PP-001 and MIL-001 and record the results as
RC-001 to RC-004. All four verdicts are Go, so their Version History
rows become Accepted and the previous rows Deprecated. MIL-002 to
MIL-004 stay Proposed.

BC-001 failed criterion 1 (cost-benefit not justified as qualitative).
Add the justification and a target-completion constraint (2026-10-14)
that PP-001 and MIL-001 are checked against.

Add the Traceability Matrix (TM-001) and register RC and TM in the
artifact registry. PP has no QC checklist, so RC-003 checks the plan
against BC-001 and the milestones instead. Author and reviewer are
both S01, a deviation noted in each record.

Refs #5
Co-Authored-By: Claude Sonnet 5.5 <noreply@anthropic.com>
Tirsvad added 1 commit 2026-10-04 17:24:23 +02:00
Tirsvad merged commit 4b1228fec0 into main 2026-10-04 17:24:34 +02:00
Sign in to join this conversation.
No Reviewers
No labels
1 Participants
Notifications
Due Date
No due date set.
Dependencies

No dependencies set.

Reference: Tirsvad-Udemy-100_days_of_code/014-higher_lower#22