Tirsvad 1d35410b8d Add planning baseline: BC, SA, PP and two gateways
Create the Business Case, Stakeholder Analysis (S01 course participant,
S02 Udemy coursists, S03 GitHub viewers), Project Plan and the milestone
documents MIL-001 (project setup, 6 tasks) and MIL-002 (game
implementation, 8 tasks) for the console Blackjack game.

Register PP and MIL in the artifact registry, set the PO language to en,
and link the synced Gitea milestones in the Gateway Schedule.

Refs #1
Refs #2
Refs #3
Refs #4
Refs #5
Refs #6
Refs #7
Refs #8
Refs #9
Refs #10
Refs #11
Refs #12
Refs #13
Refs #14
2026-10-04 21:38:09 +08:00

84 lines
3.2 KiB
Markdown

# Project Plan
## Metadata
| Key | Value |
| --- | --- |
| ID | PP-001 |
| CrossReference | [BC-001], [SA-001], [MIL-001], [MIL-002] |
## Version History
| Date | Status | Author | Reviewer | Change | Commit |
| --- | --- | --- | --- | --- | --- |
| 2026-10-04 | Accepted | Jens Tirsvad Nielsen | S01 | Initial version | pending |
---
## Purpose
Schedule the two gateways that deliver the Blackjack game within the Business Case's two-evening effort constraint ([BC-001]).
## Planning Assumptions
- Week 1 starts 2026-10-04; the plan ends by 2026-10-11.
- Phase length: setup 2 days, implementation 5 days (part-time).
- Communication follows [SA-001]: one pull request review by S01 per gateway; S02 and S03 are served by the published repository.
- PO language is English; no translated copies are kept.
## Gateway Schedule
| Gateway | Document | Window | Decision date | Owner | Stories | Main deliverable | Milestone |
| --- | --- | --- | --- | --- | --- | --- | --- |
| Gateway 1 - Project Setup | [MIL-001] | 2026-10-04 to 2026-10-06 | 2026-10-06 | S01 | none | Layout, pyproject, constants, Doxyfile, README | [Milestone-34] |
| Gateway 2 - Game Implementation | [MIL-002] | 2026-10-07 to 2026-10-11 | 2026-10-11 | S01 | none | Playable, tested, documented game | [Milestone-35] |
```plantuml
@startgantt
Project starts 2026-10-04
[Gateway 1 - Project Setup] starts 2026-10-04 and ends 2026-10-06
[Gateway 1 Go/No-Go] happens 2026-10-06
[Gateway 2 - Game Implementation] starts 2026-10-07 and ends 2026-10-11
[Gateway 2 Go/No-Go] happens 2026-10-11
@endgantt
```
## Scope Coverage
| Business Case scope item | Gateway |
| --- | --- |
| Project scaffolding and README | [MIL-001] |
| Git host description and topics | [MIL-001] |
| Game logic, emoji cards, logo, restart | [MIL-002] |
| Unit tests | [MIL-002] (smoke test in [MIL-001]) |
| Doxygen documentation | [MIL-001] (Doxyfile), [MIL-002] (comments) |
## Dependencies
```
Gateway 1 - Project Setup -> Gateway 2 - Game Implementation
```
A No-Go on Gateway 1 moves every Gateway 2 date by the same number of days.
## Plan Risks
| Risk | Impact | Mitigation |
| --- | --- | --- |
| Part-time availability | Dates slip | Dates are targets; a slip is recorded here, scope is not cut |
| Git host API token lacks permission to edit repository metadata | Task 1 of Gateway 1 blocked | Set description and topics by hand in the web UI |
## Open Issues
- No use cases or user stories are modelled: all tasks are plain technical tasks because the assignment is a small single-actor console program. Say if a use case (for example "Play a game of Blackjack") should be added first.
- The reviewer for every artifact is S01 (sole stakeholder); an independent reviewer would need a new stakeholder ID.
- No README template was supplied, so a standard layout is used.
- The Python `.gitignore` already exists in the repository and is verified in [MIL-001] task 2.
---
[BC-001]: ./business-case.md
[SA-001]: ./stakeholder-analysis.md
[MIL-001]: ./milestones/mil-001-project-setup.md
[MIL-002]: ./milestones/mil-002-game-implementation.md
[Milestone-34]: https://git.tirsystem.com/Tirsvad-Udemy-100_days_of_code/011-black-jack/milestone/34
[Milestone-35]: https://git.tirsystem.com/Tirsvad-Udemy-100_days_of_code/011-black-jack/milestone/35