# Project Plan
|
|
|
|
## Metadata
|
|
| Key | Value |
|
|
| --- | --- |
|
|
| ID | PP-001 |
|
|
| CrossReference | [MIL-001], [MIL-002], [MIL-003], [MIL-004], [SA-001], [BC-001] |
|
|
|
|
## Version History
|
|
| Date | Status | Author | Reviewer | Change | Commit |
|
|
| --- | --- | --- | --- | --- | --- |
|
|
| 2026-10-04 | Accepted | Jens Tirsvad Nielsen | S01 | Initial version | [8ccefff] |
|
|
|
|
---
|
|
|
|
## Purpose
|
|
|
|
Schedule the four phases that deliver the console calculator of Udemy's "100 Days of Code" day 10 assignment. This is a very small project, so the Business Case is short and the Stakeholder Analysis names only the Product Owner (S01); the plan, the milestones and their tasks are the whole planning trail. Each phase is one branch and one pull request, and each task is synced as an issue.
|
|
|
|
## Planning Assumptions
|
|
|
|
- Work starts 2026-10-05 and ends by 2026-10-08, one phase per day.
|
|
- Owner and reviewer are the Product Owner, S01. The review is the Product Owner accepting the document.
|
|
- Product Owner language: English.
|
|
- Python 3.13 or newer, `venv`, `src/ tests/ docs/` layout, constants in `constants.py`, Doxygen comments.
|
|
- `.env` holds a personal token used only for tooling; the project never reads or tests it.
|
|
- Nothing is committed or pushed until the Product Owner asks.
|
|
|
|
## Gateway Schedule
|
|
|
|
| Gateway | Document | Window | Decision date | Owner | Stories | Main deliverable | Milestone |
|
|
| --- | --- | --- | --- | --- | --- | --- | --- |
|
|
| Project scaffold | [MIL-001] | 2026-10-05 | 2026-10-05 | S01 | | `pyproject.toml` | |
|
|
| Calculator core | [MIL-002] | 2026-10-06 | 2026-10-06 | S01 | | `src/calc/constants.py` and `src/calc/operations.py` | |
|
|
| Console interface | [MIL-003] | 2026-10-07 | 2026-10-07 | S01 | | `src/calc/calculator.py` and `src/calc/__main__.py` | |
|
|
| Documentation and release | [MIL-004] | 2026-10-08 | 2026-10-08 | S01 | | `README.md` following the project template | |
|
|
|
|
```plantuml
|
|
@startgantt
|
|
Project starts 2026-10-05
|
|
[Project scaffold] starts 2026-10-05 and ends 2026-10-05
|
|
[Project scaffold Go/No-Go] happens 2026-10-05
|
|
[Calculator core] starts 2026-10-06 and ends 2026-10-06
|
|
[Calculator core Go/No-Go] happens 2026-10-06
|
|
[Console interface] starts 2026-10-07 and ends 2026-10-07
|
|
[Console interface Go/No-Go] happens 2026-10-07
|
|
[Documentation and release] starts 2026-10-08 and ends 2026-10-08
|
|
[Documentation and release Go/No-Go] happens 2026-10-08
|
|
@endgantt
|
|
```
|
|
|
|
## Scope Coverage
|
|
|
|
| Scope item | Gateway |
|
|
| --- | --- |
|
|
| Project configuration, layout, `.gitignore`, Doxyfile, repository metadata | [MIL-001] |
|
|
| Operations stored in a dictionary of functions, constants, tests | [MIL-002] |
|
|
| Console interaction, ASCII art, continue with result, recursion | [MIL-003] |
|
|
| README, Doxygen build, setup verification, AGPL licence | [MIL-004] |
|
|
|
|
## Dependencies
|
|
|
|
```
|
|
MIL-001 -> MIL-002 -> MIL-003 -> MIL-004
|
|
```
|
|
|
|
A No-Go moves every later date by the time needed to fix the failed criterion.
|
|
|
|
## Plan Risks
|
|
|
|
| Risk | Impact | Mitigation |
|
|
| --- | --- | --- |
|
|
| Doxygen not installed on the machine | Docs check skipped | README names it as optional |
|
|
| Recursion depth on very long sessions | Crash after many restarts | Documented limit; sessions are short |
|
|
|
|
## Open Issues
|
|
|
|
- Milestone links in the Gateway Schedule are filled in after `sync-project.sh --apply`.
|
|
|
|
---
|
|
|
|
[MIL-001]: ./milestones/mil-001-project-scaffold.md
|
|
[MIL-002]: ./milestones/mil-002-calculator-core.md
|
|
[MIL-003]: ./milestones/mil-003-console-interface.md
|
|
[MIL-004]: ./milestones/mil-004-documentation-and-release.md
|
|