Project Plan

Metadata

Key Value
ID PP-001
CrossReference MIL-001, MIL-002, MIL-003, MIL-004, SA-001, BC-001

Version History

Date Status Author Reviewer Change Commit
2026-10-04 Accepted Jens Tirsvad Nielsen S01 Initial version 8ccefff

Purpose

Schedule the four phases that deliver the console calculator of Udemy's "100 Days of Code" day 10 assignment. This is a very small project, so the Business Case is short and the Stakeholder Analysis names only the Product Owner (S01); the plan, the milestones and their tasks are the whole planning trail. Each phase is one branch and one pull request, and each task is synced as an issue.

Planning Assumptions

  • Work starts 2026-10-05 and ends by 2026-10-08, one phase per day.
  • Owner and reviewer are the Product Owner, S01. The review is the Product Owner accepting the document.
  • Product Owner language: English.
  • Python 3.13 or newer, venv, src/ tests/ docs/ layout, constants in constants.py, Doxygen comments.
  • .env holds a personal token used only for tooling; the project never reads or tests it.
  • Nothing is committed or pushed until the Product Owner asks.

Gateway Schedule

Gateway Document Window Decision date Owner Stories Main deliverable Milestone
Project scaffold MIL-001 2026-10-05 2026-10-05 S01 pyproject.toml Milestone 30
Calculator core MIL-002 2026-10-06 2026-10-06 S01 src/calc/constants.py and src/calc/operations.py Milestone 31
Console interface MIL-003 2026-10-07 2026-10-07 S01 src/calc/calculator.py and src/calc/__main__.py Milestone 32
Documentation and release MIL-004 2026-10-08 2026-10-08 S01 README.md following the project template Milestone 33
@startgantt
Project starts 2026-10-05
[Project scaffold] starts 2026-10-05 and ends 2026-10-05
[Project scaffold Go/No-Go] happens 2026-10-05
[Calculator core] starts 2026-10-06 and ends 2026-10-06
[Calculator core Go/No-Go] happens 2026-10-06
[Console interface] starts 2026-10-07 and ends 2026-10-07
[Console interface Go/No-Go] happens 2026-10-07
[Documentation and release] starts 2026-10-08 and ends 2026-10-08
[Documentation and release Go/No-Go] happens 2026-10-08
@endgantt

Scope Coverage

Scope item Gateway
Project configuration, layout, .gitignore, Doxyfile, repository metadata MIL-001
Operations stored in a dictionary of functions, constants, tests MIL-002
Console interaction, ASCII art, continue with result, recursion MIL-003
README, Doxygen build, setup verification, AGPL licence MIL-004

Dependencies

MIL-001 -> MIL-002 -> MIL-003 -> MIL-004

A No-Go moves every later date by the time needed to fix the failed criterion.

Plan Risks

Risk Impact Mitigation
Doxygen not installed on the machine Docs check skipped README names it as optional
Recursion depth on very long sessions Crash after many restarts Documented limit; sessions are short

Open Issues

  • Milestone links in the Gateway Schedule are filled in after sync-project.sh --apply.