TirSystem/git-workflows: Publish wiki / publish-wiki (push) Skipped
TirSystem/git-workflows: Release / release (pull_request) Successful in 21s
TirSystem/git-workflows: Validate / validate (pull_request) Successful in 37s
TirSystem/git-workflows: OpenGrep / opengrep (pull_request) Successful in 4m19s
TirSystem/git-workflows: Sync GitHub mirror metadata / sync-metadata (push) Successful in 15s
TirSystem/git-workflows: Publish accepted milestones / publish (push) Successful in 42s
TirSystem/git-workflows: Validate / validate (push) Successful in 40s
TirSystem/git-workflows: OpenGrep / opengrep (push) Successful in 5m43s
5.8 KiB
5.8 KiB
RC-003 review
Metadata
| Key | Value |
|---|---|
| ID | RC-003 |
| CrossReference | PP-001, QC-PP-001 |
Version History
| Date | Status | Author | Reviewer | Change | Commit |
|---|---|---|---|---|---|
| 2026-11-06 | Accepted | Jens Tirsvad Nielsen | AI as stand-in for S01 | Initial version | fe0f272 |
Artifact Under Review
- Instance reviewed: PP-001
- Checklist used: QC-PP-001
- Scope: full review
- Language and domain: en / it
- Language reviewer: none, the reviewer reads English and knows the IT domain
- Mode: autonomous, not independent (the reviewer is
AI as stand-in for S01)
Checklist Results
| # | Criterion | Status | Evidence/Notes |
|---|---|---|---|
| 1 | The plan states its start date, end date and the constraint it must fit | Pass | Start 2026-11-06, end 2026-11-16, fits the Duration constraint of BC-001 |
| 2 | Every milestone or gateway is listed once with its document, decision date and owner | Pass | Four gateways, each once, with document, decision date and owner S01 |
| 3 | Every decision date lies inside the plan's window and is consistent with the dates in the linked MIL-* document |
Pass | Decision dates 11-08, 11-10, 11-12, 11-16 equal the MIL target dates and lie in the window |
| 4 | Every in-scope item of the Business Case is delivered at a named gateway (scope coverage) | Pass | Scope Coverage maps every In Scope item to MIL-001 to MIL-004 |
| 5 | Dependencies between gateways are stated, acyclic and consistent with the schedule order | Pass | Chain MIL-001 → MIL-002 → MIL-003 → MIL-004 is acyclic and matches the dates |
| 6 | The plan states what happens to later gateways and to the end date when a gateway is No-Go | Pass | Dependencies section: a No-Go moves later dates and the end date; S01 decides |
| 7 | Owners, reviewers and escalation roles use Stakeholder Analysis IDs and match the governance RACI | Pass | Owner S01 only; no GOV exists in this project, so there is no RACI to cross-check |
| 8 | Planning assumptions are listed with their source, and a changed baseline is recorded with its reason | Pass | Assumptions list their source, including the planner's date estimate accepted by S01 |
| 9 | Plan risks are listed with impact and a mitigation, and trace to Business Case risks where they come from there | Pass | Two plan risks with impact, mitigation and the BC-001 risk they come from |
| 10 | Open issues are listed, and none contradicts a statement elsewhere in the plan | Pass | Open issues are current: repository URL, no use cases, wiki location; none contradicts the plan |
| 11 | Each gateway's main deliverable is stated and matches the deliverable of its MIL-* document |
Pass | Each deliverable matches its MIL Deliverable section in substance |
| 12 | Gateways that deliver user stories name them, and those that do not say why | Pass | Stories column says "none (technical tasks)" |
| 13 | The schedule view (table, Gantt) and the dependency view agree with each other | Pass | Gantt bars and table dates agree; the chain matches the dependency list |
| 14 | Each gateway is linked to its issue-tracker milestone, or marked as not yet synced | Pass | Milestone column blank and stated as not yet synced |
| 15 | The plan is a singleton: one Project Plan per project, changes recorded in Version History | Pass | One Project Plan, PP-001, with a Version History |
Language and Domain Results
| # | Criterion | Status | Evidence/Notes |
|---|---|---|---|
| 1 | The Metadata table has a Language row and a Domain row, and neither is a placeholder |
Pass | Metadata has `Language |
| 2 | Language is a BCP 47 code and Domain is a value from the registry's domain list |
Pass | en is BCP 47; it is in the registry domain list |
| 3 | The content (prose and table cells) is written in the stated language | Pass | PP-001 prose and table cells are in English |
| 4 | The register matches the one the registry gives for the artifact type | Pass | Register is IT Executive English for BC, PP and MIL, IT Professional English for SA, as the registry gives |
| 5 | Domain terms are the PO terms of the domain's dictionary, with no synonyms | Pass | Only standard IT terms are used (Flask, route, decorator, test); the project has no DICT and no PO-specific term needs one |
| 6 | Metadata keys, section headings, IDs and statuses are in English | Pass | Metadata keys, headings, IDs and statuses are English |
| 7 | No translated twin (<name>.<language>.md) exists beside the document |
Pass | No .en.md/.da.md twin exists beside the document |
| 8 | A change of language or domain since the previous accepted version has a Version History row and was reviewed again | Pass | No change of language or domain; this is the first version |
| 9 | A reviewer competent in the domain, and in the language, has confirmed that the domain terms are used correctly | Pass | AI as stand-in for S01 read the terms as correct IT usage; S01 accepted the plan in chat on 2026-11-06. Stand-in decision, not independent; open to challenge in the run summary |
| 10 | Abbreviations are spelled out on first use, in the stated language | Pass | Abbreviations (BC, SA, MIL, GIF, HTML, PR) are spelled out or are standard IT abbreviations |
Overall Verdict
Go — All Mandatory criteria pass after the plan was corrected before review (No-Go effect, risk traceability, stories reason); no blocking finding.
Action Items
| Action | Owner | Due |
|---|---|---|
| None | S01 | 2026-11-06 |