TirSystem/git-workflows: OpenGrep / opengrep (push) Skipped
TirSystem/git-workflows: Sync GitHub mirror metadata / sync-metadata (push) Skipped
TirSystem/git-workflows: Publish accepted milestones / publish (push) Skipped
TirSystem/git-workflows: Validate / validate (push) Skipped
TirSystem/git-workflows: Release / release (pull_request) Successful in 17s
TirSystem/git-workflows: Validate / validate (pull_request) Successful in 32s
TirSystem/git-workflows: Publish wiki / publish-wiki (push) Skipped
TirSystem/git-workflows: OpenGrep / opengrep (pull_request) Successful in 4m16s
4.6 KiB
4.6 KiB
Project Plan
Metadata
| Key | Value |
|---|---|
| ID | PP-001 |
| CrossReference | BC-001, SA-001, MIL-001, MIL-002, MIL-003 |
| Language | en |
| Domain | it |
Version History
| Date | Status | Author | Reviewer | Change | Commit |
|---|---|---|---|---|---|
| 2026-11-06 | Deprecated | Jens Tirsvad Nielsen | S01 | Initial version | a07d05b |
| 2026-11-06 | Accepted | Jens Tirsvad Nielsen | S01 | Informal review against QC-PP-001 fixed 7 defects (constants.py gateway, No-Go rule, sources, risk trace, stories, sync mark); accepted by S01 as Product Owner through the accepted plan in chat on 2026-11-06 | a07d05b |
Purpose
This plan schedules three gateways that take the lecture-054 exercise from an empty repository to a tested, documented solution with a three-language wiki, within the Business Case constraint of finishing by 2026-11-09.
Planning Assumptions
- The plan starts 2026-11-06 and ends by 2026-11-09 (source: BC-001 Constraints, target 2026-11-09).
- Phase length: one working session per gateway (source: the author, from the scope of BC-001).
- One branch and one pull request per gateway, so that the steps stay traceable.
- Stakeholder S01 owns and reviews every gateway (SA-001).
Gateway Schedule
| Gateway | Document | Window | Decision date | Owner | Stories | Main deliverable | Milestone |
|---|---|---|---|---|---|---|---|
| Project baseline and repository | MIL-001 | 2026-11-06 | 2026-11-06 | S01 | none (technical tasks, see ADR-0001) | Project configuration, README, Doxyfile, ADR-0001, repository metadata | not yet synced |
| Speed calc decorator | MIL-002 | 2026-11-06 to 2026-11-07 | 2026-11-07 | S01 | none (technical tasks, see ADR-0001) | Working package, tests, one screenshot per lecture step | not yet synced |
| Wiki in three languages | MIL-003 | 2026-11-07 to 2026-11-09 | 2026-11-09 | S01 | none (technical tasks, see ADR-0001) | Wiki pages in en, da, ms explaining each lecture step | not yet synced |
@startgantt
Project starts 2026-11-06
[Project baseline] starts 2026-11-06 and ends 2026-11-06
[Project baseline Go/No-Go] happens 2026-11-06
[Speed calc decorator] starts 2026-11-06 and ends 2026-11-07
[Speed calc decorator Go/No-Go] happens 2026-11-07
[Wiki] starts 2026-11-07 and ends 2026-11-09
[Wiki Go/No-Go] happens 2026-11-09
@endgantt
Scope Coverage
| Business Case scope item | Gateway |
|---|---|
pyproject.toml, .gitignore, Doxyfile |
MIL-001 |
constants.py |
MIL-002 |
| README with venv and test instructions | MIL-001, updated in MIL-002 |
| Repository description and topics | MIL-001 |
Python package under src/, tests under tests/ |
MIL-002 |
| One screenshot per lecture step | MIL-002 |
| Wiki in en, da, ms | MIL-003 |
Dependencies
MIL-001 → MIL-002 → MIL-003
A No-Go stops the later gateways; their dates move by the same number of days. S01, as Product Owner, decides whether the end date of 2026-11-09 moves; a move beyond it changes the constraint in BC-001 and needs a new version of it.
Plan Risks
| Risk | Impact | Mitigation |
|---|---|---|
| The wiki is not enabled on the git host (assumption of BC-001) | MIL-003 cannot be published | Task checks the setting early; stop and report if disabled |
| Screenshots need a rendering tool (relates to the screenshot risk of BC-001) | Delay in MIL-002 | Render from captured output with a dev-only tool, no host desktop |
| Timing tests are flaky (risk of BC-001) | False failures in MIL-002 | Tests inject a fake clock; checked by Go criterion 1 of MIL-002 |
The token in .env leaks (risk of BC-001) |
Account compromise during MIL-001 | .env is git-ignored; checked by Go criterion 2 of MIL-001 |
Open Issues
- The request names the repository
Tirsvad-Udemy-100_days_of_code, butoriginisTirsvad-Udemy-100-days-of-code/054-speed-calc-decorator. The plan usesorigin. - User stories and use cases are skipped: the exercise is one function with no user interaction. The reason is recorded in ADR-0001 (task in MIL-001).
- Under autonomous mode the reviews of S01's documents are performed by the AI as stand-in for S01 and are recorded as not independent.