Project Plan: Snack and Lift Booking Bot
Metadata
| Key | Value |
|---|---|
| ID | PP-001 |
| CrossReference | BC-001, SA-001, MIL-001, MIL-002, MIL-003, MIL-004, MIL-005, MIL-006, MIL-007, MIL-008, MIL-009, MIL-010 |
| Language | en |
| Domain | it |
Version History
| Date | Status | Author | Reviewer | Change | Commit |
|---|---|---|---|---|---|
| 2026-10-28 | Accepted | Jens Tirsvad Nielsen | S01 | Add MIL-009, a verification fix found in a real run (S01 accepted the plan in chat) | 3b9e381 |
| 2026-10-28 | Accepted | Jens Tirsvad Nielsen | S01 | Add MIL-010, gym accounts from a credentials file (S01 asked for it in chat) | 434bdaf |
Purpose
This plan schedules ten gateways (MIL-001 to MIL-010) that take the Snack and Lift booking bot from an accepted baseline to a documented, tested and published repository. The Business Case sets no deadline, so the window 2026-10-28 to 2026-11-06 is a planning assumption of this plan. Each gateway ends in a decision and a deliverable and is delivered by one pull request on its own branch.
Planning Assumptions
- Week 1 starts 2026-10-28; the plan ends by 2026-11-06 (a planning assumption, see Open Issues).
- Phase length: one to two days per gateway. Gateways 003 to 007 follow the Udemy lecture steps 1 to 9.
- One branch and one pull request per gateway, each closing the issues of its tasks.
- The user stories and use case steps of the journey are skipped for this project (ADR-0001), so no gateway lists stories.
- Autonomous mode: S01 accepts this plan in chat; the AI acts as stand-in reviewer (S02) and records it in each
RC-*.
Gateway Schedule
| Gateway | Document | Window | Decision date | Owner | Stories | Main deliverable | Milestone |
|---|---|---|---|---|---|---|---|
| Baseline and repository set-up | MIL-001 | 2026-10-28 | 2026-10-28 | S01 | none (documents) | Accepted baseline, ADRs, repository description and topics | |
| Project scaffold and tooling | MIL-002 | 2026-10-28 to 2026-10-29 | 2026-10-29 | S01 | none (technical tasks) | pyproject.toml, layout, .gitignore, Doxyfile, README, Docker image |
|
| Lecture steps 1 and 2 | MIL-003 | 2026-10-29 to 2026-10-30 | 2026-10-30 | S01 | none (technical tasks) | Chrome profile, navigation, login(), screenshots 1 and 2 |
|
| Lecture steps 3 and 4 | MIL-004 | 2026-10-30 to 2026-10-31 | 2026-10-31 | S01 | none (technical tasks) | Card parsing, booking, state checks, screenshots 3 and 4 | |
| Lecture steps 5 and 6 | MIL-005 | 2026-10-31 to 2026-11-01 | 2026-11-01 | S01 | none (technical tasks) | Counters, summary, Tuesday and Thursday list, screenshots 5 and 6 | |
| Lecture steps 7 and 8 | MIL-006 | 2026-11-01 to 2026-11-02 | 2026-11-02 | S01 | none (technical tasks) | My Bookings verification, time travel, screenshots 7 and 8 | |
| Lecture step 9 | MIL-007 | 2026-11-02 to 2026-11-04 | 2026-11-04 | S01 | none (technical tasks) | retry, resilient login, book_class, get_my_bookings, screenshot 9 |
|
| Documentation, wiki and release | MIL-008 | 2026-11-04 to 2026-11-06 | 2026-11-06 | S01 | none (documentation) | README, Doxygen, wiki in en, da and ms, final checks | |
| Verification fix | MIL-009 | 2026-11-04 to 2026-11-06 | 2026-11-06 | S01 | none (technical tasks) | Verification compares only the window of the run; new screenshots 7 to 9 | |
| Gym accounts from a file | MIL-010 | 2026-11-04 to 2026-11-06 | 2026-11-06 | S01 | none (technical tasks) | .env.gym credentials for the student and the admin account |
@startgantt
Project starts 2026-10-28
[Baseline] starts 2026-10-28 and ends 2026-10-28
[Scaffold] starts 2026-10-28 and ends 2026-10-29
[Steps 1 and 2] starts 2026-10-29 and ends 2026-10-30
[Steps 3 and 4] starts 2026-10-30 and ends 2026-10-31
[Steps 5 and 6] starts 2026-10-31 and ends 2026-11-01
[Steps 7 and 8] starts 2026-11-01 and ends 2026-11-02
[Step 9] starts 2026-11-02 and ends 2026-11-04
[Documentation] starts 2026-11-04 and ends 2026-11-06
[Baseline Go/No-Go] happens 2026-10-28
[Scaffold Go/No-Go] happens 2026-10-29
[Steps 1 and 2 Go/No-Go] happens 2026-10-30
[Steps 3 and 4 Go/No-Go] happens 2026-10-31
[Steps 5 and 6 Go/No-Go] happens 2026-11-01
[Steps 7 and 8 Go/No-Go] happens 2026-11-02
[Step 9 Go/No-Go] happens 2026-11-04
[Release Go/No-Go] happens 2026-11-06
@endgantt
Scope Coverage
| Business Case scope item | Gateway |
|---|---|
| Selenium bot for the practice site, with the assignment's function names | MIL-003, MIL-004, MIL-006, MIL-007 |
| Lecture steps 1 to 9 | MIL-003 (1, 2), MIL-004 (3, 4), MIL-005 (5, 6), MIL-006 (7, 8), MIL-007 (9) |
Python project files: src/, tests/, docs/, pyproject.toml, constants.py, .gitignore, Doxyfile, README |
MIL-002, MIL-008 |
Unit tests with pytest |
MIL-002 to MIL-007 |
| One screenshot per lecture step in README and wiki | MIL-003 to MIL-007 (capture), MIL-008 (use) |
| Wiki in en, da and ms | MIL-008 |
| Repository description and topics | MIL-001 |
Dependencies
MIL-001 → MIL-002 → MIL-003 → MIL-004 → MIL-005 → MIL-006 → MIL-007 → MIL-008 → MIL-009 → MIL-010
A No-Go on a gateway stops all later gateways until it is fixed and re-reviewed. The end date then moves by the days spent on the rework; S01 decides a move of the end date.
Plan Risks
| Risk | Impact | Mitigation |
|---|---|---|
| The practice site changes its page structure (Business Case risk: site changes) | Steps 3 to 9 need rework | Selectors only in constants.py; the first task of MIL-003 records the page as seen |
| The container starts with an empty site database (state lives in the browser profile) | Login and booking cannot be shown | MIL-003 registers a documented test account in a profile volume; browser runs reset data through the admin page |
| Stand-in review misses a defect | Defect reaches main |
RC-* marks the review as not independent; S01 reviews the final summary |
| Translations take longer than planned | MIL-008 slips | Write English first; da and ms follow page by page; no extra pages |
Open Issues
- Target repository: the user names
https://git.tirsystem.com/Tirsvad-Udemy-100_days_of_code, butoriginisTirsvad-Udemy-100-days-of-code/049-snack-and-lift. The plan usesorigin(description and topics are set there) until S01 states otherwise in chat. - The Business Case sets no deadline; the window 2026-10-28 to 2026-11-06 is this plan's own assumption.
- No QC checklist exists for accepting the Project Plan beyond
QC-PP-001; S01's acceptance of the plan in chat accepts the row.