Project Plan

Metadata

Key Value
ID PP-001
CrossReference BC-001, SA-001, MIL-001, MIL-002, MIL-003, MIL-004, MIL-005, MIL-006
Language en
Domain it

Version History

Date Status Author Reviewer Change Commit
2026-10-28 Deprecated Jens Tirsvad Nielsen AI as stand-in for S01 Initial version (reviewed in RC-003) 96a9a78
2026-10-28 Accepted Jens Tirsvad Nielsen AI as stand-in for S01 Added MIL-006 purchase strategy improvement after the user asked for it in chat (reviewed in RC-015) 638730d

Purpose

This plan schedules the six phases that deliver the Cookie Clicker bot inside the one-week limit of BC-001.

Planning Assumptions

  • Week 1 starts 2026-10-28; the plan ends by 2026-11-04, per the Business Case constraint.
  • Phase length: one to three days, one branch and one pull request per phase.
  • S01 owns every phase; the AI acts as stand-in reviewer for S01 in autonomous mode, recorded in each review.
  • The communication cadence of SA-001 is one pull request per phase and a final summary.

Gateway Schedule

Gateway Document Window Decision date Owner Stories Main deliverable Milestone
Project setup and tooling MIL-001 2026-10-28 to 2026-10-29 2026-10-29 S01 none (technical tasks) pyproject, skeleton, .gitignore, Doxyfile, repository metadata
Bot core MIL-002 2026-10-29 to 2026-10-30 2026-10-30 S01 none (technical tasks) open_game, click_cookie, get_cookie_count with tests
Upgrades and run MIL-003 2026-10-30 to 2026-10-31 2026-10-31 S01 none (technical tasks) strategy, run_bot, main
Screenshots and README MIL-004 2026-10-31 to 2026-11-02 2026-11-02 S01 none (technical tasks) Docker run, screenshots, README
Wiki and release MIL-005 2026-11-02 to 2026-11-04 2026-11-04 S01 none (technical tasks) Wiki en, da, ms and final checks
Purchase strategy improvement MIL-006 2026-10-28 to 2026-11-03 2026-11-03 S01 none (technical tasks) Reliable store visits, upgrades bought, a higher CPS in Docker, README and wiki updated
@startgantt
Project starts 2026-10-28
[Project setup] starts 2026-10-28 and ends 2026-10-29
[Bot core] starts 2026-10-29 and ends 2026-10-30
[Upgrades and run] starts 2026-10-30 and ends 2026-10-31
[Screenshots and README] starts 2026-10-31 and ends 2026-11-02
[Wiki and release] starts 2026-11-02 and ends 2026-11-04
[MIL-001 Go/No-Go] happens 2026-10-29
[MIL-002 Go/No-Go] happens 2026-10-30
[MIL-003 Go/No-Go] happens 2026-10-31
[MIL-004 Go/No-Go] happens 2026-11-02
[Purchase strategy] starts 2026-10-28 and ends 2026-11-03
[MIL-005 Go/No-Go] happens 2026-11-04
[MIL-006 Go/No-Go] happens 2026-11-03
@endgantt

Scope Coverage

Business Case scope item Gateway
Bot for the lecture steps MIL-002, MIL-003
pyproject, .gitignore, .venv instructions, Doxyfile, constants.py MIL-001, MIL-004
pytest tests with a fake game MIL-002, MIL-003
Headless Docker run and screenshots MIL-004
README MIL-004
Wiki in en, da and ms MIL-005
Description and topics on the git host MIL-001
Higher CPS by a more reliable purchase strategy (objective O1) MIL-006

Dependencies

MIL-001 → MIL-002 → MIL-003 → MIL-004 → MIL-005 → MIL-006

MIL-006 was added after the first release; it runs beside the end of the window and must finish by 2026-11-03, one day before the end date.

A No-Go on a phase returns it to its owner for rework and moves every later gateway by the rework time; the end date 2026-11-04 moves only if S01 decides so and records the reason in Planning Assumptions. S01 is owner, reviewer and the only escalation point.

Plan Risks

Risk Impact Mitigation
The live game changes or is unreachable during MIL-004 Screenshots and the CPS run slip Run the capture early in MIL-004; stop and report if it stays unreachable
Translation takes longer than planned MIL-005 slips Danish and Bahasa Malaysia follow the English page by page, with a short page set
Repository name differs from the one in the request Metadata set on the wrong repository Use the repository origin points to; reported in the plan summary
Token handling (Business Case risk: a token leaks) Secret exposure Tokens only read from .env by scripts outside the project, never printed
Live game changes (Business Case risk: page structure changes) Bot breaks Ids in constants.py; run the capture early in MIL-004
The new strategy does not raise the CPS MIL-006 returns No-Go Measure after each change; keep the first release as the fallback

Open Issues

  • The request names https://git.tirsystem.com/Tirsvad-Udemy-100_days_of_code (underscores); origin is Tirsvad-Udemy-100-days-of-code/048-the-coockie-factory. The plan applies description and topics to the origin repository.
  • The Product Owner's earlier solution targeted the old Orteil page and used the extra package continuous_threading; this project reimplements it for the current game with one loop and no extra dependency.

Traceability Analysis

Business Goal Alignment

Stakeholder Concern Business Case objective
S01 CN-001, CN-002, CN-007 O1, O4
S02 CN-003, CN-004 O2, O3, O4
S03 CN-005, CN-006 O4, O5

Sign-Off

Stakeholder Decision Date
S01 Pending acceptance of this plan in chat