Project Plan: Cookie Clicker Bot
Metadata
| Key | Value |
|---|---|
| ID | PP-001 |
| CrossReference | BC-001, SA-001 |
| Language | en |
| Domain | it |
Version History
| Date | Status | Author | Reviewer | Change | Commit |
|---|---|---|---|---|---|
| 2026-10-28 | Accepted | Jens Tirsvad Nielsen | S01 | Initial version: seven gateways; accepted by S01 in chat | cadc5ef |
| 2026-10-28 | Accepted | Jens Tirsvad Nielsen | S01 | Add MIL-008 (smarter purchase rule); accepted by S01 in chat | 9a6796f |
Purpose
This plan schedules eight gateways (MIL-001 to MIL-008) that take the Cookie Clicker bot from an accepted baseline to a documented, tested and published repository. The Business Case sets no deadline, so the window 2026-10-28 to 2026-11-04 is a planning assumption of this plan. Each gateway ends in a decision and a deliverable and is delivered by one pull request on its own branch.
Planning Assumptions
- Week 1 starts 2026-10-28; the plan ends by 2026-11-04 (a planning assumption, see Open Issues).
- Phase length: one day per gateway, except the baseline and documentation, which are longer. Gateways 003 to 006 follow the Udemy lecture steps 1 to 5.
- One branch and one pull request per gateway, each closing the issues of its tasks.
- The user stories and use case steps of the journey are skipped for this project (ADR-0001), so no gateway lists stories.
- Autonomous mode: S01 accepts this plan in chat; the AI acts as stand-in reviewer and records it in each
RC-*.
Gateway Schedule
| Gateway | Document | Window | Decision date | Owner | Stories | Main deliverable | Milestone |
|---|---|---|---|---|---|---|---|
| Baseline and repository set-up | MIL-001 | 2026-10-28 | 2026-10-28 | S01 | none (documents) | Accepted baseline, ADRs, repository description and topics | Milestone 1 |
| Project scaffold and tooling | MIL-002 | 2026-10-28 to 2026-10-29 | 2026-10-29 | S01 | none (technical tasks) | pyproject.toml, layout, .gitignore, Doxyfile, README, Docker image |
Milestone 2 |
| Lecture steps 1 and 2 | MIL-003 | 2026-10-29 to 2026-10-30 | 2026-10-30 | S01 | none (technical tasks) | Open game, dismiss language, click cookie, screenshots 1 and 2 | Milestone 3 |
| Lecture step 3 | MIL-004 | 2026-10-30 to 2026-10-31 | 2026-10-31 | S01 | none (technical tasks) | Parsing, selection rule, purchase every 5 s, screenshot 3 | Milestone 4 |
| Lecture step 4 | MIL-005 | 2026-10-31 to 2026-11-01 | 2026-11-01 | S01 | none (technical tasks) | 5 minute run, cookies per second, screenshot 4 | Milestone 5 |
| Lecture step 5 | MIL-006 | 2026-11-01 to 2026-11-02 | 2026-11-02 | S01 | none (technical tasks) | Strategy options, comparison, screenshot 5 | Milestone 6 |
| Documentation, wiki and release | MIL-007 | 2026-11-02 to 2026-11-04 | 2026-11-04 | S01 | none (documentation) | README, Doxygen, wiki in en, da and ms, final checks | Milestone 7 |
| Smarter purchase rule | MIL-008 | 2026-11-05 to 2026-11-06 | 2026-11-06 | S01 | none (technical tasks) | Best value strategy, measured comparison, wiki note in en, da and ms | Milestone 8 |
@startgantt
Project starts 2026-10-28
[Baseline] starts 2026-10-28 and ends 2026-10-28
[Scaffold] starts 2026-10-28 and ends 2026-10-29
[Steps 1 and 2] starts 2026-10-29 and ends 2026-10-30
[Step 3] starts 2026-10-30 and ends 2026-10-31
[Step 4] starts 2026-10-31 and ends 2026-11-01
[Step 5] starts 2026-11-01 and ends 2026-11-02
[Documentation] starts 2026-11-02 and ends 2026-11-04
[Baseline Go/No-Go] happens 2026-10-28
[Scaffold Go/No-Go] happens 2026-10-29
[Steps 1 and 2 Go/No-Go] happens 2026-10-30
[Step 3 Go/No-Go] happens 2026-10-31
[Step 4 Go/No-Go] happens 2026-11-01
[Step 5 Go/No-Go] happens 2026-11-02
[Release Go/No-Go] happens 2026-11-04
@endgantt
Scope Coverage
| Business Case scope item | Gateway |
|---|---|
| Selenium bot for the game, with the assignment's function names | MIL-003, MIL-004, MIL-005 |
| Lecture steps 1 to 5 | MIL-003 (1 and 2), MIL-004 (3), MIL-005 (4), MIL-006 (5) |
Python project files: src/, tests/, docs/, pyproject.toml, constants.py, .gitignore, Doxyfile, README |
MIL-002, MIL-007 |
Unit tests with pytest |
MIL-002 to MIL-006 |
| One screenshot per lecture step in README and wiki | MIL-003 to MIL-006 (capture), MIL-007 (use) |
| Wiki in en, da and ms | MIL-007 |
| Repository description and topics | MIL-001 |
Dependencies
MIL-001 → MIL-002 → MIL-003 → MIL-004 → MIL-005 → MIL-006 → MIL-007
A No-Go on a gateway stops all later gateways until it is fixed and re-reviewed. The end date then moves by the days spent on the rework; S01 decides a move of the end date.
Plan Risks
| Risk | Impact | Mitigation |
|---|---|---|
| The game changes its page structure (Business Case risk: page changes) | Steps 1 to 4 need rework | Selectors only in constants.py; the first task records the page as seen |
| The headless container cannot run the game well | Screenshots and the 5 minute run are late | Try the container in MIL-002; pin Chromium; fall back to a shorter duration constant for tests only |
| Stand-in review misses a defect | Defect reaches main |
RC-* marks the review as not independent; S01 reviews the final summary |
| Translations take longer than planned | MIL-007 slips | Write English first; da and ms follow page by page; no extra pages |
Open Issues
- Resolved: S01 accepted the plan in chat on 2026-10-28; the target repository is
origin, as S01 confirmed.