Project Plan: Cookie Clicker Bot

Metadata

Key Value
ID PP-001
CrossReference BC-001, SA-001
Language en
Domain it

Version History

Date Status Author Reviewer Change Commit
2026-10-28 Accepted Jens Tirsvad Nielsen S01 Add MIL-008 (smarter purchase rule); accepted by S01 in chat 9a6796f
2026-10-29 Accepted Jens Tirsvad Nielsen S01 Add MIL-009 (Home pages show the best value result); accepted by S01 in chat 72faffa

Purpose

This plan schedules nine gateways (MIL-001 to MIL-009) that take the Cookie Clicker bot from an accepted baseline to a documented, tested and published repository. The Business Case sets no deadline, so the window 2026-10-28 to 2026-11-04 is a planning assumption of this plan. Each gateway ends in a decision and a deliverable and is delivered by one pull request on its own branch.

Planning Assumptions

  • Week 1 starts 2026-10-28; the plan ends by 2026-11-04 (a planning assumption, see Open Issues).
  • Phase length: one day per gateway, except the baseline and documentation, which are longer. Gateways 003 to 006 follow the Udemy lecture steps 1 to 5.
  • One branch and one pull request per gateway, each closing the issues of its tasks.
  • The user stories and use case steps of the journey are skipped for this project (ADR-0001), so no gateway lists stories.
  • Autonomous mode: S01 accepts this plan in chat; the AI acts as stand-in reviewer and records it in each RC-*.

Gateway Schedule

Gateway Document Window Decision date Owner Stories Main deliverable Milestone
Baseline and repository set-up MIL-001 2026-10-28 2026-10-28 S01 none (documents) Accepted baseline, ADRs, repository description and topics Milestone 1
Project scaffold and tooling MIL-002 2026-10-28 to 2026-10-29 2026-10-29 S01 none (technical tasks) pyproject.toml, layout, .gitignore, Doxyfile, README, Docker image Milestone 2
Lecture steps 1 and 2 MIL-003 2026-10-29 to 2026-10-30 2026-10-30 S01 none (technical tasks) Open game, dismiss language, click cookie, screenshots 1 and 2 Milestone 3
Lecture step 3 MIL-004 2026-10-30 to 2026-10-31 2026-10-31 S01 none (technical tasks) Parsing, selection rule, purchase every 5 s, screenshot 3 Milestone 4
Lecture step 4 MIL-005 2026-10-31 to 2026-11-01 2026-11-01 S01 none (technical tasks) 5 minute run, cookies per second, screenshot 4 Milestone 5
Lecture step 5 MIL-006 2026-11-01 to 2026-11-02 2026-11-02 S01 none (technical tasks) Strategy options, comparison, screenshot 5 Milestone 6
Documentation, wiki and release MIL-007 2026-11-02 to 2026-11-04 2026-11-04 S01 none (documentation) README, Doxygen, wiki in en, da and ms, final checks Milestone 7
Smarter purchase rule MIL-008 2026-11-05 to 2026-11-06 2026-11-06 S01 none (technical tasks) Best value strategy, measured comparison, wiki note in en, da and ms Milestone 8
Home pages show the best value result MIL-009 2026-10-29 to 2026-10-30 2026-10-30 S01 none (documentation) Results row and --best-value note on the wiki Home pages in en, da and ms Milestone 9
@startgantt
Project starts 2026-10-28
[Baseline] starts 2026-10-28 and ends 2026-10-28
[Scaffold] starts 2026-10-28 and ends 2026-10-29
[Steps 1 and 2] starts 2026-10-29 and ends 2026-10-30
[Step 3] starts 2026-10-30 and ends 2026-10-31
[Step 4] starts 2026-10-31 and ends 2026-11-01
[Step 5] starts 2026-11-01 and ends 2026-11-02
[Documentation] starts 2026-11-02 and ends 2026-11-04
[Baseline Go/No-Go] happens 2026-10-28
[Scaffold Go/No-Go] happens 2026-10-29
[Steps 1 and 2 Go/No-Go] happens 2026-10-30
[Step 3 Go/No-Go] happens 2026-10-31
[Step 4 Go/No-Go] happens 2026-11-01
[Step 5 Go/No-Go] happens 2026-11-02
[Release Go/No-Go] happens 2026-11-04
@endgantt

Scope Coverage

Business Case scope item Gateway
Selenium bot for the game, with the assignment's function names MIL-003, MIL-004, MIL-005
Lecture steps 1 to 5 MIL-003 (1 and 2), MIL-004 (3), MIL-005 (4), MIL-006 (5)
Python project files: src/, tests/, docs/, pyproject.toml, constants.py, .gitignore, Doxyfile, README MIL-002, MIL-007
Unit tests with pytest MIL-002 to MIL-006
One screenshot per lecture step in README and wiki MIL-003 to MIL-006 (capture), MIL-007 (use)
Wiki in en, da and ms MIL-007
Repository description and topics MIL-001

Dependencies

MIL-001 → MIL-002 → MIL-003 → MIL-004 → MIL-005 → MIL-006 → MIL-007

A No-Go on a gateway stops all later gateways until it is fixed and re-reviewed. The end date then moves by the days spent on the rework; S01 decides a move of the end date.

Plan Risks

Risk Impact Mitigation
The game changes its page structure (Business Case risk: page changes) Steps 1 to 4 need rework Selectors only in constants.py; the first task records the page as seen
The headless container cannot run the game well Screenshots and the 5 minute run are late Try the container in MIL-002; pin Chromium; fall back to a shorter duration constant for tests only
Stand-in review misses a defect Defect reaches main RC-* marks the review as not independent; S01 reviews the final summary
Translations take longer than planned MIL-007 slips Write English first; da and ms follow page by page; no extra pages

Open Issues

  • Resolved: S01 accepted the plan in chat on 2026-10-28; the target repository is origin, as S01 confirmed.