Purpose
This plan schedules the seven milestones of the Musical Time Machine project inside the Business Case window of 2026-10-28 to 2026-11-30 (BC-001, Constraints).
Planning Assumptions
- Week 1 starts 2026-10-28; the plan ends by 2026-11-30, per the Business Case constraint.
- One milestone is one branch and one pull request; a milestone is as long as its tasks need, between 4 and 9 days.
- Reviews are done by the AI as stand-in for S01 (SA-001, S01); the language criteria of
QC-LANG-001 that need a person stay open until S01 confirms them.
- Live steps 2 to 4 need S01's
browser.json; the dates of MIL-004 to MIL-006 assume it exists by 2026-11-14.
Gateway Schedule
| Gateway |
Document |
Window |
Decision date |
Owner |
Stories |
Main deliverable |
Milestone |
| Planning baseline |
MIL-001 |
2026-10-28 to 2026-11-02 |
2026-11-02 |
S01 |
none (technical tasks) |
Accepted BC-001 |
Milestone 1 |
| Project scaffold |
MIL-002 |
2026-11-03 to 2026-11-06 |
2026-11-06 |
S01 |
none (technical tasks) |
A project skeleton with `pyproject |
Milestone 2 |
| Step 1 - Scrape the Billboard Hot 100 |
MIL-003 |
2026-11-07 to 2026-11-12 |
2026-11-12 |
S01 |
none (technical tasks) |
A command that asks for a date in YYYY-MM-DD format |
Milestone 3 |
| Step 2 - YouTube Music authentication |
MIL-004 |
2026-11-13 to 2026-11-17 |
2026-11-17 |
S01 |
none (technical tasks) |
A client adapter around ytmusicapi that reads `browser |
Milestone 4 |
| Step 3 - Create the playlist |
MIL-005 |
2026-11-18 to 2026-11-20 |
2026-11-20 |
S01 |
none (technical tasks) |
A create_playlist use case that returns the id of an existing or new private playlist |
Milestone 5 |
| Step 4 - Search and add songs |
MIL-006 |
2026-11-21 to 2026-11-25 |
2026-11-25 |
S01 |
none (technical tasks) |
An add_songs use case that searches with the song filter and adds the top result |
Milestone 6 |
| Wiki and release |
MIL-007 |
2026-11-26 to 2026-11-30 |
2026-11-30 |
S01 |
none (technical tasks) |
Wiki pages in docs/wiki/ in English |
Milestone 7 |
Scope Coverage
| Business Case scope item |
Gateway |
| Repository description and topics |
MIL-001 |
pyproject.toml, .venv instructions, constants.py, Doxygen, README from the template, .gitignore |
MIL-002 |
| Scraping of Bakeboard into a list (O1) |
MIL-003 |
| YouTube Music authentication (O2) |
MIL-004 |
| Playlist creation without duplicates (O3) |
MIL-005 |
| Search and add songs (O4) |
MIL-006 |
| Wiki in en, da, ms and the step screenshots (O5) |
MIL-003 to MIL-007 |
Dependencies
A No-Go on a gateway returns it to rework and moves every later date by the rework time; the end date 2026-11-30 moves only if S01 decides so in chat.
Plan Risks
| Risk |
Impact |
Mitigation |
browser.json not available by 2026-11-14 |
MIL-004 to MIL-006 cannot be closed |
The run stops and reports; tests with fakes are finished so only the live screenshots wait |
| Language criteria need a person |
Baseline stays Go-with-conditions |
Ask S01 to confirm criteria 3, 5 and 9 of QC-LANG-001 when accepting the plan |
| Bakeboard offline during the live run |
Step 1 screenshot delayed |
The stored fixture proves the code; the screenshot is taken later |
Open Issues
- The owner of the repository on the git host: the
origin remote uses Tirsvad-Udemy-100-days-of-code, the request names Tirsvad-Udemy-100_days_of_code; the remote is used until S01 says otherwise.
- Whether the live steps 2 to 4 can be run depends on
browser.json from S01.