Project Plan

Metadata

Key Value
ID PP-001
CrossReference BC-001, SA-001, MIL-001, MIL-002, MIL-003
Language en
Domain it

Version History

Date Status Author Reviewer Change Commit
2026-10-17 Accepted Jens Tirsvad Nielsen S01 Initial version; accepted by S01 (AI as stand-in, plan accepted in chat 2026-10-17) pending

Purpose

This plan schedules the three phases that deliver the birthday wisher of BC-001: project setup, the core program, and documentation with publication. It is scheduled against the Business Case constraint of one pull request per milestone.

Planning Assumptions

  • Work starts 2026-10-17 and the plan ends by 2026-10-20.
  • Each phase is one day; each phase is one branch and one pull request that closes its issues.
  • Autonomous mode: the AI runs all phases after the user accepts this plan; the review of each artifact is by S01's stand-in and recorded as not independent (SA-001).

Gateway Schedule

Gateway Document Window Decision date Owner Stories Main deliverable Milestone
G1 Project setup MIL-001 2026-10-17 to 2026-10-18 2026-10-18 S01 none (plain tasks) Skeleton, tooling, repository metadata
G2 Core MIL-002 2026-10-18 to 2026-10-19 2026-10-19 S01 none (plain tasks) Working, tested birthday wisher
G3 Documentation MIL-003 2026-10-19 to 2026-10-20 2026-10-20 S01 none (plain tasks) README, tri-lingual wiki, screenshots
@startgantt
Project starts 2026-10-17
[G1 Project setup] starts 2026-10-17 and ends 2026-10-18
[G2 Core] starts 2026-10-18 and ends 2026-10-19
[G3 Documentation] starts 2026-10-19 and ends 2026-10-20
[G1 Go/No-Go] happens 2026-10-18
[G2 Go/No-Go] happens 2026-10-19
[G3 Go/No-Go] happens 2026-10-20
@endgantt

Scope Coverage

Business Case scope item Gateway
CSV reading, matching, letters, SMTP sending G2
src/, tests/, constants.py, pyproject.toml, .gitignore, .env.example, Doxyfile G1
Repository description and topics G1
README and wiki in en, da, ms with screenshots G3

Dependencies

G1 Project setup -> G2 Core -> G3 Documentation

A No-Go at a gate moves every later date by the time needed to fix and re-review it.

Plan Risks

Risk Impact Mitigation
The git host token cannot set topics or merge Gate G1 or the merge is blocked Stop and report; the user supplies or fixes the token
A screenshot cannot be produced without the host desktop G3 delayed Render terminal output to an image with a script, never on the host desktop
Danish or Malay translation quality Readers misled Keep sentences short, keep code in English; S01 can challenge in the run summary

Open Issues

  • The repository named in the request (https://git.tirsystem.com/Tirsvad-Udemy-100_days_of_code) is the organisation; the project is published to this clone's origin, Tirsvad-Udemy-100-days-of-code/032-birthday-wisher. Please confirm.
  • No use case or user story is written: the tasks are plain technical tasks for a one-feature learning project, so the plan-first gate is met through the "plain technical task" route. Say so if a use case should be written.
  • The course hints use pandas; the project uses the standard csv module (no runtime dependencies, objective in BC-001).
  • Support for 29 February birthdays is decided during G2 and documented.