Tirsvad 0126093601 Implement the birthday wisher core (MIL-002)
Layered package (domain, application, infrastructure, presentation), CLI with
--dry-run and --today, SMTP with STARTTLS behind a port, 56 offline tests and
the Python code review RC-006.

Task: MIL-002#1
Task: MIL-002#2
Task: MIL-002#3
Task: MIL-002#4
Task: MIL-002#5
Task: MIL-002#6
Refs #7
Refs #8
Refs #9
Refs #10
Refs #11
Refs #12
2026-10-17 15:37:16 +08:00
Tirsvad 70b2b3c02f Merge pull request 'MIL-001: project setup' (#19) from mil-001-project-setup into main
TirSystem/github-action: Sync GitHub mirror metadata / sync-metadata (push) Successful in 6s
2026-10-17 09:31:35 +02:00
Tirsvad 9b3a134721 Merge pull request 'Plan baseline: Business Case, Stakeholder Analysis, Project Plan, milestones' (#1) from plan-baseline into main
TirSystem/github-action: Sync GitHub mirror metadata / sync-metadata (push) Successful in 6s
2026-10-17 09:31:09 +02:00
Tirsvad 6d5aa89cd8 Set up the project skeleton (MIL-001)
pyproject.toml (Python >=3.13, no runtime dependencies, pytest as dev extra),
Python .gitignore, .env.example, constants.py, assignment data files,
Doxyfile and a smoke test.

Task: MIL-001#1
Task: MIL-001#2
Task: MIL-001#3
Task: MIL-001#4
Refs #2
Refs #3
Refs #4
Refs #5
2026-10-17 15:15:06 +08:00
Tirsvad 887d27c476 Resolve pending commit links 2026-10-17 15:11:26 +08:00
Tirsvad 052008f213 Add baseline: Business Case, Stakeholder Analysis, Project Plan and milestones
Refs the three milestones MIL-001 to MIL-003; reviews RC-001 to RC-005 (Go).
2026-10-17 15:11:20 +08:00
Tirsvad f8ea3401bd Initial commit 2026-10-17 09:03:39 +02:00