Project Plan: Flash Card
Metadata
| Key | Value |
|---|---|
| ID | PP-001 |
| CrossReference | BC-001, SA-001, US-001, MIL-001, MIL-002, MIL-003, MIL-004, MIL-005, MIL-006, MIL-007, MIL-008, MIL-009, MIL-010, MIL-011, MIL-012 |
| Language | en |
| Domain | it |
Version History
| Date | Status | Author | Reviewer | Change | Commit |
|---|---|---|---|---|---|
| 2026-10-15 | Deprecated | Jens Tirsvad Nielsen | AI as stand-in for S01 | Added gateway MIL-011 Menu bar (new request of S01) | 2211d0f |
| 2026-10-15 | Accepted | Jens Tirsvad Nielsen | AI as stand-in for S01 | Added gateway MIL-012 Release v0.2.0 (new request of S01) | 0264b60 |
Purpose
This plan schedules the seven phases (gateways) that deliver the flash card program inside the delivery window of one week that the Business Case sets as a constraint (2026-10-14 to 2026-10-21). Each phase is one milestone and is delivered by one pull request, so the Product Owner (S01) can follow the work step by step.
Planning Assumptions
- Week 1 starts 2026-10-14; the plan ends by 2026-10-21, per the Business Case constraint.
- One phase takes one day; the last phase (documentation and publication) has three days because the wiki exists in three languages and the screenshots need the finished program.
- The baseline documents (Business Case, Stakeholder Analysis, Project Plan, use case documents, ADRs) are accepted before MIL-001 starts, in a pull request of their own.
- Phases 2 to 5 follow the four steps of the course assignment in order; phase 6 is the Product Owner's extra.
- S01 is owner and approving reviewer of every phase; in autonomous mode the AI acts as stand-in and the review records say so.
Gateway Schedule
| Gateway | Document | Window | Decision date | Owner | Stories | Main deliverable | Milestone |
|---|---|---|---|---|---|---|---|
| Project foundation | MIL-001 | 2026-10-14 | 2026-10-14 | S01 | none | pyproject, gitignore, skeleton, Doxyfile, first README, word list | Milestone MIL-001 |
| Step 1 - User interface | MIL-002 | 2026-10-15 | 2026-10-15 | S01 | US-001.01 | The window with card and buttons | Milestone MIL-002 |
| Step 2 - New flash cards | MIL-003 | 2026-10-16 | 2026-10-16 | S01 | US-001.02 | Random cards from the word list | Milestone MIL-003 |
| Step 3 - Flip the cards | MIL-004 | 2026-10-17 | 2026-10-17 | S01 | US-001.03 | Flip after 3000 ms | Milestone MIL-004 |
| Step 4 - Save progress | MIL-005 | 2026-10-18 | 2026-10-18 | S01 | US-001.04 | words_to_learn.csv | Milestone MIL-005 |
| Spoken Malay word | MIL-006 | 2026-10-19 | 2026-10-19 | S01 | US-001.05 | Text to speech as optional extra | Milestone MIL-006 |
| Documentation and publication | MIL-007 | 2026-10-19 to 2026-10-21 | 2026-10-21 | S01 | none | README, screenshots, wiki in 3 languages, description and topics | Milestone MIL-007 |
| Choose level | MIL-008 | 2026-10-20 | 2026-10-20 | S01 | US-001.06 | A level choice (100, 1000, all words) before the cards; documents, wiki and screenshots updated | |
| Executable with PyInstaller | MIL-009 | 2026-10-16 | 2026-10-16 | S01 | US-001.07 | One Windows executable that runs without Python, built by a script; documents, wiki and README updated | |
| Release v0.1.0 | MIL-010 | 2026-10-16 | 2026-10-16 | S01 | US-001.08 | Tag v0.1.0 and a release with flash-card.exe, its checksum and release notes |
|
| Menu bar | MIL-011 | 2026-10-17 | 2026-10-17 | S01 | US-001.09 to US-001.12 | File menu (open word list, change level, reset word list, exit) and About menu (contact); documents, wiki and screenshots updated | |
| Release v0.2.0 | MIL-012 | 2026-10-18 | 2026-10-18 | S01 | US-001.08 | Version 0.2.0, tag v0.2.0 and a release with the menu bar, notes and, if the host accepts it, the executable |
@startgantt
Project starts 2026-10-14
[Foundation] starts 2026-10-14 and ends 2026-10-14
[Step 1 UI] starts 2026-10-15 and ends 2026-10-15
[Step 2 Cards] starts 2026-10-16 and ends 2026-10-16
[Step 3 Flip] starts 2026-10-17 and ends 2026-10-17
[Step 4 Progress] starts 2026-10-18 and ends 2026-10-18
[Speech] starts 2026-10-19 and ends 2026-10-19
[Documentation] starts 2026-10-19 and ends 2026-10-21
[Foundation Go/No-Go] happens 2026-10-14
[Step 1 Go/No-Go] happens 2026-10-15
[Step 2 Go/No-Go] happens 2026-10-16
[Step 3 Go/No-Go] happens 2026-10-17
[Step 4 Go/No-Go] happens 2026-10-18
[Speech Go/No-Go] happens 2026-10-19
[Documentation Go/No-Go] happens 2026-10-21
[Choose level] starts 2026-10-20 and ends 2026-10-20
[Choose level Go/No-Go] happens 2026-10-20
[Executable] starts 2026-10-16 and ends 2026-10-16
[Executable Go/No-Go] happens 2026-10-16
[Release] starts 2026-10-16 and ends 2026-10-16
[Release Go/No-Go] happens 2026-10-16
[Menu bar] starts 2026-10-17 and ends 2026-10-17
[Menu bar Go/No-Go] happens 2026-10-17
[Release 0.2.0] starts 2026-10-18 and ends 2026-10-18
[Release 0.2.0 Go/No-Go] happens 2026-10-18
@endgantt
Scope Coverage
| Business Case scope item | Gateway |
|---|---|
| Tkinter program with the assignment's function names | MIL-002, MIL-003, MIL-004, MIL-005 |
Reading data/ms-da.csv |
MIL-003 |
Saving and using words_to_learn.csv |
MIL-005 |
| Optional spoken Malay word | MIL-006 |
pyproject.toml, .gitignore, Doxyfile, .venv instructions, pytest, constants.py |
MIL-001 |
| README, screenshots, wiki in three languages | MIL-007 |
| Repository description and topics | MIL-007 |
| Choice of level (new request after MIL-007) | MIL-008 |
| Executable built with PyInstaller (new request after MIL-008) | MIL-009 |
| Release with the executable attached (new request after MIL-009) | MIL-010 |
| Menu bar with File and About menus (new request after MIL-009) | MIL-011 |
| Release v0.2.0 with the menu bar (new request after MIL-011) | MIL-012 |
| Framework documents of the baseline | Baseline pull request before MIL-001 |
Dependencies
Baseline → MIL-001 → MIL-002 → MIL-003 → MIL-004 → MIL-005 → MIL-006 → MIL-007 → MIL-008 → MIL-009 → MIL-010 → MIL-011 → MIL-012
A No-Go on a phase moves every later date by the days the rework takes; MIL-008 was added after MIL-007 and takes the unplanned day 2026-10-20, so no buffer is left inside the window; a No-Go moves the end date past 2026-10-21 and S01 decides whether to accept that.
Plan Risks
| Risk | Impact | Mitigation |
|---|---|---|
| No display on the machine that runs the review, so the e2e tests skip | Window behaviour is checked by the view model tests only | The review record states whether the e2e tests ran; the screenshots in MIL-007 prove the window on a machine with a display |
| The git host's CI is not available | The publish workflows cannot run | Milestones are published with sync-project.sh and the wiki by SSH push (MIL-007) |
| The speech extra cannot be installed on the build machine | MIL-006 cannot be demonstrated end to end | The adapter is tested with fakes; the manual check is recorded as not done |
Open Issues
- No Governance document (GOV): see ADR-0003. S01 is the only approver.
- The git host's
sync-milestonesworkflow is not installed; whether to install it is S01's decision.