# Project Plan: Flash Card
|
|
|
|
## Metadata
|
|
| Key | Value |
|
|
| --- | --- |
|
|
| ID | PP-001 |
|
|
| CrossReference | [BC-001], [SA-001], [US-001], [MIL-001], [MIL-002], [MIL-003], [MIL-004], [MIL-005], [MIL-006], [MIL-007] |
|
|
| Language | en |
|
|
| Domain | it |
|
|
|
|
## Version History
|
|
| Date | Status | Author | Reviewer | Change | Commit |
|
|
| --- | --- | --- | --- | --- | --- |
|
|
| 2026-10-14 | Accepted | Jens Tirsvad Nielsen | AI as stand-in for S01 | Initial version | [c3fbcbc] |
|
|
|
|
---
|
|
|
|
## Purpose
|
|
|
|
This plan schedules the seven phases (gateways) that deliver the flash card program inside the delivery window of one week that the Business Case sets as a constraint (2026-10-14 to 2026-10-21). Each phase is one milestone and is delivered by one pull request, so the Product Owner (S01) can follow the work step by step.
|
|
|
|
## Planning Assumptions
|
|
|
|
- Week 1 starts 2026-10-14; the plan ends by 2026-10-21, per the Business Case constraint.
|
|
- One phase takes one day; the last phase (documentation and publication) has three days because the wiki exists in three languages and the screenshots need the finished program.
|
|
- The baseline documents (Business Case, Stakeholder Analysis, Project Plan, use case documents, ADRs) are accepted before MIL-001 starts, in a pull request of their own.
|
|
- Phases 2 to 5 follow the four steps of the course assignment in order; phase 6 is the Product Owner's extra.
|
|
- S01 is owner and approving reviewer of every phase; in autonomous mode the AI acts as stand-in and the review records say so.
|
|
|
|
## Gateway Schedule
|
|
|
|
| Gateway | Document | Window | Decision date | Owner | Stories | Main deliverable | Milestone |
|
|
| --- | --- | --- | --- | --- | --- | --- | --- |
|
|
| Project foundation | [MIL-001] | 2026-10-14 | 2026-10-14 | S01 | none | pyproject, gitignore, skeleton, Doxyfile, first README, word list | [Milestone MIL-001][MS-001] |
|
|
| Step 1 - User interface | [MIL-002] | 2026-10-15 | 2026-10-15 | S01 | US-001.01 | The window with card and buttons | [Milestone MIL-002][MS-002] |
|
|
| Step 2 - New flash cards | [MIL-003] | 2026-10-16 | 2026-10-16 | S01 | US-001.02 | Random cards from the word list | [Milestone MIL-003][MS-003] |
|
|
| Step 3 - Flip the cards | [MIL-004] | 2026-10-17 | 2026-10-17 | S01 | US-001.03 | Flip after 3000 ms | [Milestone MIL-004][MS-004] |
|
|
| Step 4 - Save progress | [MIL-005] | 2026-10-18 | 2026-10-18 | S01 | US-001.04 | words_to_learn.csv | [Milestone MIL-005][MS-005] |
|
|
| Spoken Malay word | [MIL-006] | 2026-10-19 | 2026-10-19 | S01 | US-001.05 | Text to speech as optional extra | [Milestone MIL-006][MS-006] |
|
|
| Documentation and publication | [MIL-007] | 2026-10-19 to 2026-10-21 | 2026-10-21 | S01 | none | README, screenshots, wiki in 3 languages, description and topics | [Milestone MIL-007][MS-007] |
|
|
|
|
```plantuml
|
|
@startgantt
|
|
Project starts 2026-10-14
|
|
[Foundation] starts 2026-10-14 and ends 2026-10-14
|
|
[Step 1 UI] starts 2026-10-15 and ends 2026-10-15
|
|
[Step 2 Cards] starts 2026-10-16 and ends 2026-10-16
|
|
[Step 3 Flip] starts 2026-10-17 and ends 2026-10-17
|
|
[Step 4 Progress] starts 2026-10-18 and ends 2026-10-18
|
|
[Speech] starts 2026-10-19 and ends 2026-10-19
|
|
[Documentation] starts 2026-10-19 and ends 2026-10-21
|
|
[Foundation Go/No-Go] happens 2026-10-14
|
|
[Step 1 Go/No-Go] happens 2026-10-15
|
|
[Step 2 Go/No-Go] happens 2026-10-16
|
|
[Step 3 Go/No-Go] happens 2026-10-17
|
|
[Step 4 Go/No-Go] happens 2026-10-18
|
|
[Speech Go/No-Go] happens 2026-10-19
|
|
[Documentation Go/No-Go] happens 2026-10-21
|
|
@endgantt
|
|
```
|
|
|
|
## Scope Coverage
|
|
|
|
| Business Case scope item | Gateway |
|
|
| --- | --- |
|
|
| Tkinter program with the assignment's function names | MIL-002, MIL-003, MIL-004, MIL-005 |
|
|
| Reading `data/ms-da.csv` | MIL-003 |
|
|
| Saving and using `words_to_learn.csv` | MIL-005 |
|
|
| Optional spoken Malay word | MIL-006 |
|
|
| `pyproject.toml`, `.gitignore`, `Doxyfile`, `.venv` instructions, `pytest`, `constants.py` | MIL-001 |
|
|
| README, screenshots, wiki in three languages | MIL-007 |
|
|
| Repository description and topics | MIL-007 |
|
|
| Framework documents of the baseline | Baseline pull request before MIL-001 |
|
|
|
|
## Dependencies
|
|
|
|
```
|
|
Baseline → MIL-001 → MIL-002 → MIL-003 → MIL-004 → MIL-005 → MIL-006 → MIL-007
|
|
```
|
|
|
|
A No-Go on a phase moves every later date by the days the rework takes; the buffer is the 2026-10-20 working day, which has no phase of its own.
|
|
|
|
## Plan Risks
|
|
|
|
| Risk | Impact | Mitigation |
|
|
| --- | --- | --- |
|
|
| No display on the machine that runs the review, so the e2e tests skip | Window behaviour is checked by the view model tests only | The review record states whether the e2e tests ran; the screenshots in MIL-007 prove the window on a machine with a display |
|
|
| The git host's CI is not available | The publish workflows cannot run | Milestones are published with `sync-project.sh` and the wiki by SSH push (MIL-007) |
|
|
| The speech extra cannot be installed on the build machine | MIL-006 cannot be demonstrated end to end | The adapter is tested with fakes; the manual check is recorded as not done |
|
|
|
|
## Open Issues
|
|
|
|
- No Governance document (GOV): see ADR-0003. S01 is the only approver.
|
|
- The git host's `sync-milestones` workflow is not installed; whether to install it is S01's decision.
|
|
|
|
---
|
|
|
|
[BC-001]: ./business-case.md
|
|
[SA-001]: ./stakeholder-analysis.md
|
|
[US-001]: ./user-stories.md
|
|
[MIL-001]: ./milestones/mil-001-foundation.md
|
|
[MIL-002]: ./milestones/mil-002-step1-user-interface.md
|
|
[MIL-003]: ./milestones/mil-003-step2-new-flash-cards.md
|
|
[MIL-004]: ./milestones/mil-004-step3-flip-cards.md
|
|
[MIL-005]: ./milestones/mil-005-step4-save-progress.md
|
|
[MIL-006]: ./milestones/mil-006-malay-speech.md
|
|
[MIL-007]: ./milestones/mil-007-documentation-and-publication.md
|
|
[c3fbcbc]: https://git.tirsystem.com/Tirsvad-Udemy-100-days-of-code/031-flash-card/commit/c3fbcbcfaf799e0ae34aed7e14d3bc8a62f03db3
|
|
[MS-001]: https://git.tirsystem.com/Tirsvad-Udemy-100-days-of-code/031-flash-card/milestone/165
|
|
[MS-002]: https://git.tirsystem.com/Tirsvad-Udemy-100-days-of-code/031-flash-card/milestone/166
|
|
[MS-003]: https://git.tirsystem.com/Tirsvad-Udemy-100-days-of-code/031-flash-card/milestone/167
|
|
[MS-004]: https://git.tirsystem.com/Tirsvad-Udemy-100-days-of-code/031-flash-card/milestone/168
|
|
[MS-005]: https://git.tirsystem.com/Tirsvad-Udemy-100-days-of-code/031-flash-card/milestone/169
|
|
[MS-006]: https://git.tirsystem.com/Tirsvad-Udemy-100-days-of-code/031-flash-card/milestone/170
|
|
[MS-007]: https://git.tirsystem.com/Tirsvad-Udemy-100-days-of-code/031-flash-card/milestone/171
|