Project Plan
Metadata
Version History
| Date |
Status |
Author |
Reviewer |
Change |
Commit |
| 2026-10-13 |
Accepted |
Jens Tirsvad Nielsen |
S01 |
Initial version |
f1b3c03 |
| 2026-10-13 |
Proposed |
Jens Tirsvad Nielsen |
AI as stand-in for S01 |
CrossReference: added US-001 |
259d017 |
Purpose
This plan schedules the four phases that deliver the squirrel census assignment: tooling, analysis, documentation and wiki publication. It schedules them against the Business Case constraint of one pull request per milestone and a single-day effort.
Planning Assumptions
- Week 1 starts 2026-10-13 (the day of the plan); the plan ends by 2026-10-16.
- Phase length: one day per phase.
- One branch and one pull request per milestone, each closing the issues of its tasks (BC-001 Constraints).
- The Product Owner and reviewer is S01 for every phase (SA-001); in autonomous mode the AI acts as stand-in and records it in each review record.
- The plan is accepted by S01 in chat; the Project Plan has no quality control (QC) checklist.
Gateway Schedule
| Gateway |
Document |
Window |
Decision date |
Owner |
Stories |
Main deliverable |
Milestone |
| G1 Project scaffold and tooling |
MIL-001 |
2026-10-13 to 2026-10-14 |
2026-10-14 |
S01 |
none |
.gitignore, pyproject.toml, constants, Doxyfile, continuous integration (CI), repository metadata |
Milestone 124 |
| G2 Squirrel census analysis |
MIL-002 |
2026-10-14 to 2026-10-15 |
2026-10-15 |
S01 |
US-001 |
Package, tests, census file, squirrel_count.csv |
Milestone 125 |
| G3 README, source documentation and screenshots |
MIL-003 |
2026-10-15 to 2026-10-16 |
2026-10-16 |
S01 |
none |
README, Doxygen comments, screenshots |
Milestone 126 |
| G4 Wiki and publication |
MIL-004 |
2026-10-16 |
2026-10-16 |
S01 |
none |
Wiki in en, da and ms |
Milestone 127 |
Scope Coverage
| Business Case scope item |
Gateway |
| Reading the census file and counting by primary fur colour |
G2 |
Summary table exported as squirrel_count.csv |
G2 |
Command line entry point, constants.py, pyproject.toml, .gitignore, tests, CI |
G1 and G2 |
Doxygen comments, Doxyfile, build instructions |
G1 and G3 |
| README, screenshots |
G3 |
| Three-language wiki |
G4 |
| Repository description and topics |
G1 (set) and G4 (verified) |
Dependencies
A No-Go at a gateway stops the later gateways; their dates move by the days the rework takes.
Plan Risks
| Risk |
Impact |
Mitigation |
| CI runner is not available on the git host |
The CI workflow cannot be shown green |
Run the same commands locally and report the missing runner |
| Wiki repository cannot be pushed |
G4 deliverable is not published |
Keep the pages under docs/wiki/ and report it |
| Doxygen is not installed locally |
The documentation build cannot be verified |
Report as not verified; document the command |
Open Issues
- The repository URL in the request (
Tirsvad-Udemy-100_days_of_code) differs from origin (Tirsvad-Udemy-100-days-of-code/025-squirrel); the plan follows origin.
- The census file (730 kilobytes) is assumed to be committed under
data/; S01 can veto this at plan acceptance.
- The lecture uses Pandas; the plan uses the standard library to keep zero runtime dependencies (ADR-0001, SA-001 conflict list).