Project Plan: Snake Game (Day 24)
Metadata
| Key | Value |
|---|---|
| ID | PP-001 |
| CrossReference | BC-001, SA-001, DICT-001, MIL-001, MIL-002, MIL-003, MIL-004, MIL-005 |
| Language | en |
| Domain | it |
Version History
| Date | Status | Author | Reviewer | Change | Commit |
|---|---|---|---|---|---|
| 2026-10-13 | Accepted | Jens Tirsvad Nielsen | S01 | Initial version; accepted by S01 (Product Owner) in chat on 2026-10-13 | pending |
Purpose
This plan schedules the five milestones that deliver the Snake Game (Day 24) repository of BC-001. The repository starts from the finished main of 021-snake-game, which holds the snake game of days 20 and 21 with tests and documentation. The milestones therefore set up the repository, adopt that base, add continuous play and the high score of the day-24 lectures, store the high score in data.txt, and finish the repository with the README check and a wiki in three languages. Each milestone is one gateway document, one branch and one pull request, so that every step is kept track of and reviewed before the next one starts.
Planning Assumptions
- The phase starts 2026-10-14 and ends by 2026-10-25, which leaves two days of buffer after MIL-005. All dates are proposed and need the Product Owner's confirmation (see Open Issues).
- Phase length: two days per milestone, sized for the spare time of S01, who owns every phase (SA-001).
- The starting point is the finished
mainof 021-snake-game, which S01 pointed to in chat on 2026-10-13. The base is copied file by file, so each adopted file is a task, and every difference from the base is listed in the pull request. - One branch per milestone, named after it (
mil-001-project-foundationand so on), and one pull request that closes the issues of that milestone with oneCloses #Nline each. The planning documents themselves are delivered on the branchplan-baseline. - S01 switched on autonomous mode in chat on 2026-10-13 (see
AGENTS.md, Modes): S01's acceptance of this plan is the request, and the commit, the push, the pull request and its merge follow without further asking. The reviews are done by the assistant as stand-in for S01 and are not independent; each record saysMode: autonomous, not independent. - The plan gate is enabled for commits in this clone: a commit that changes
src/ortests/needs aTask: MIL-NNN#Ntrailer for an accepted, reviewed milestone. - The tokens in
.envare used only by commands that the assistant runs (repository description and topics, sync of issues); the project never imports, tests or tracks the file.
Gateway Schedule
| Gateway | Document | Window | Decision date | Owner | Stories | Main deliverable | Milestone |
|---|---|---|---|---|---|---|---|
| Project foundation | MIL-001 | 2026-10-14 to 2026-10-15 | 2026-10-15 | S01 | None (see Open Issues) | pyproject.toml, .gitignore, constants.py, README, Doxyfile, CI workflow, repository description and topics |
|
| Adopt the game | MIL-002 | 2026-10-16 to 2026-10-17 | 2026-10-17 | S01 | None (see Open Issues) | Snake, Food, Scoreboard, the main flow and python -m snake_game, with their tests |
|
| Continuous play and high score | MIL-003 | 2026-10-18 to 2026-10-19 | 2026-10-19 | S01 | None (see Open Issues) | Scoreboard.high_score and reset, Snake.reset, play without game over, with tests |
|
| High score file | MIL-004 | 2026-10-20 to 2026-10-21 | 2026-10-21 | S01 | None (see Open Issues) | High score read from and written to data.txt with with, robust against a missing or damaged file, with tests |
|
| Wiki and finish | MIL-005 | 2026-10-22 to 2026-10-23 | 2026-10-23 | S01 | None (see Open Issues) | Wiki in English, Danish and Bahasa Melayu; README checked against the finished game; end-to-end verification |
@startgantt
Project starts 2026-10-14
[MIL-001 Project foundation] starts 2026-10-14 and ends 2026-10-15
[MIL-002 Adopt the game] starts 2026-10-16 and ends 2026-10-17
[MIL-003 Continuous play and high score] starts 2026-10-18 and ends 2026-10-19
[MIL-004 High score file] starts 2026-10-20 and ends 2026-10-21
[MIL-005 Wiki and finish] starts 2026-10-22 and ends 2026-10-23
[MIL-001 Go/No-Go] happens 2026-10-15
[MIL-002 Go/No-Go] happens 2026-10-17
[MIL-003 Go/No-Go] happens 2026-10-19
[MIL-004 Go/No-Go] happens 2026-10-21
[MIL-005 Go/No-Go] happens 2026-10-23
[Buffer] starts 2026-10-24 and ends 2026-10-25
@endgantt
Scope Coverage
| Business Case scope item | Gateway |
|---|---|
| Adopting the finished game of the base: configuration, constants, workflow | MIL-001 |
Adopting the finished game of the base: Snake, Food, Scoreboard, the main flow and the tests |
MIL-002 |
Day-24 lecture "High score": high_score attribute, reset instead of game_over, scoreboard text |
MIL-003 |
Day-24 lecture "Continuous play": no stop on collision; Snake.reset moves the old segments off the screen |
MIL-003 |
Day-24 lectures "Open, read and write files" and "Persist the high score": data.txt, with, conversion to int, write on new high score |
MIL-004 |
| Robust file handling (missing, empty or damaged file) | MIL-004 |
Constants in constants.py; src/, tests/, docs/ layout |
MIL-001, extended in MIL-003 and MIL-004 |
pyproject.toml, Python .gitignore, Doxyfile, README, continuous integration workflow |
MIL-001, README updated in MIL-002 to MIL-004 and finished in MIL-005 |
| Repository description and topics | MIL-001 (task 7), checked again in MIL-005 |
| Wiki in English, Danish and Bahasa Melayu | MIL-005 |
Dependencies
MIL-001 → MIL-002 → MIL-003 → MIL-004 → MIL-005
A No-Go on a gateway returns it to S01 for rework and moves every later date by the same number of days; the two buffer days after MIL-005 absorb a slip before the end date moves.
Plan Risks
| Risk | Impact | Mitigation |
|---|---|---|
| The planning documents take longer to review than the work left on the game | The first gateway slips | Review BC-001, SA-001 and this plan together in one sitting; keep the milestones small |
| Author and reviewer are the same person (S01) | A review can miss a defect | Use the QC checklists and the pull request as the second look; recorded in BC-001 |
| The git host has no Actions runner | The CI workflow is never executed | Run the same commands locally before each pull request |
| Lecture details are only available as the summaries in the request | The game differs from the video | S01 compares the finished game with the video at the MIL-003 and MIL-004 Go/No-Go |
| The sync matches issues by title, so a title used twice overwrites an issue | A task disappears from the board | Every task title is unique across all milestones; check before each --apply |
| The base is a copy of another repository | A later fix reaches only one of them | Out of scope by decision (see BC-001); each pull request lists the differences from the base |
| The wiki publish workflow needs a secret of the organization | The wiki stays empty | Reported to S01, never worked around; the pages are files in wiki/ and are not lost |
Open Issues
- Dates: the start date, milestone lengths and the end date 2026-10-25 are proposed and not given by the Product Owner; confirm or replace them.
- Product Owner (PO) language: S01 chose English on 2026-10-13;
enis recorded indocs/artifact-registry.md. - Stakeholder levels: the Power and Interest levels of S02 and S03 in SA-001 are proposals, taken over from 021-snake-game.
- Starting point: the finished
mainof 021-snake-game is the base, as S01 pointed to it in chat on 2026-10-13. Confirm that it is the intended base and not a rebuild from 020-snake-game. - Repository address: the request names
https://git.tirsystem.com/Tirsvad-Udemy-100_days_of_code(underscores), which is not the repository oforigin(Tirsvad-Udemy-100-days-of-code/024-snake). S01 choseoriginin chat on 2026-10-13; description and topics are set there. - Repository description and topics: the proposed text is in MIL-001; S01 confirms it by accepting this plan.
- "Python greater than 3.13": read as Python 3.13 or newer (
requires-python = ">=3.13"), as in 021-snake-game. Confirm. - README template: the Product Owner's README template is used. It differs from
framework/templates/README-template.md, soframework/scripts/check-readme.shstays off. - Place of
data.txt: the lecture opens the plain namedata.txt, which is resolved against the current working directory, so the game started from another folder uses another file. MIL-004 keeps the lecture's name as the default and makes the path a parameter; the alternative is a fixed place per user. Confirm.data.txtis listed in.gitignore, because it is the player's own state. - Robust file handling: the lecture assumes
data.txtexists and holds a number. The plan adds a fallback to 0 (objective 6 of BC-001) and creates a missing file. Confirm, or ask for the lecture's version without it. - Mail merge project: the request lists the personalised-letters project of day 24. It is a separate program and out of scope here (see BC-001); it can get its own repository.
- Display-free tests:
Scoreboardinherits fromTurtle, so its tests install a faketurtlemodule, as in 021-snake-game. - No user story or use case: the tasks are written as build and check steps, so they are plain technical tasks. If the player's goal should be modelled, add a Use Case Diagram, a user story and a use case and reference them from the task rows.
- Governance and traceability matrix:
GOVandTMdo not exist yet in this project. Decide whether to create them; the plan proceeds without them and records each review as anRC-*. The Domain Dictionary DICT-001 was added on 2026-10-13 so that criterion 5 ofQC-LANG-001can be checked. - Screenshot: not part of this plan; a screenshot needs S01's display. It can be added to the README and the wiki later.
- Diagram check: the Gantt chart above was not rendered because no PlantUML server is configured (
PLANTUML_URL); render it before the review. - Sync:
sync-project.sh --applyis run withGITEA_TOKENfrom the personal.envafter the plan is accepted, as in 021-snake-game; the sync matches issues by title.