Adds the Business Case, Stakeholder Analysis, Domain Dictionary, Project Plan and milestones MIL-001 to MIL-003, with the review records RC-001 to RC-006 (all Go). The repository starts from the finished main of 020-snake-game, as S01 decided on 2026-10-08. The milestones and their 22 issues were synced to the git host.
2026-10-08 17:46:38 +08:00

71 lines
6.0 KiB
Markdown

# RC-002: Review of SA-001
## Metadata
| Key | Value |
| --- | --- |
| ID | RC-002 |
| CrossReference | [SA-001], [QC-SA-001], [QC-LANG-001], [BC-001], [DICT-001], [PP-001] |
## Version History
| Date | Status | Author | Reviewer | Change | Commit |
| --- | --- | --- | --- | --- | --- |
| 2026-10-08 | Proposed | Jens Tirsvad Nielsen | S01 | Initial version | pending |
---
## Artifact Under Review
- Instance reviewed: [SA-001]
- Checklist used: [QC-SA-001] and, for the language and domain, [QC-LANG-001]
- Scope: full review
- Language and domain: en / it
- Language reviewer: none (S01 reads English and knows the IT domain)
## Checklist Results
| # | Criterion | Status | Evidence/Notes |
| --- | --- | --- | --- |
| 1 | Power/Interest grid is filled for every stakeholder, with no gaps or unclassified entries | Pass | S01, S02 and S03 each have a Power Level, an Interest Level and a Quadrant. |
| 2 | Each stakeholder is assigned a unique, stable ID (e.g. S01-S11 style) reusable for RACI assignments in other artifacts | Pass | S01 to S03; the milestones and review records use them as owner and reviewer. |
| 3 | Roles and organizational context are defined with explicit Power and Interest levels, not just narrative description | Pass | Role, Organization, Power and Interest are table columns. The levels of S02 and S03 were not stated by the Product Owner; the Purpose says they are proposals, and the Project Plan lists them as an open issue. |
| 4 | Communication needs (channel, frequency, deliverable type) are mapped to project phases or milestones | Pass | Communication Requirements table maps S01, S02 and S03 to channel, frequency, deliverable and the milestones MIL-001 and MIL-003. |
| 5 | Conflicting stakeholder interests are identified with documented mitigation or resolution strategies | Pass | Three conflicts, each with a mitigation (lecture style against structure; nothing to install against pytest and Doxygen; author equals reviewer). |
| 6 | Stakeholder concerns are explicitly traced to Business Case objectives | Pass | Business Goal Alignment table; the objective numbers (1, 2 to 4, 5, 6, 7, 8, 9, 10) were checked against the ten objectives of BC-001 and match. |
| 7 | Primary concerns are expressed in both business language and a recognized quality-attribute mapping (e.g. FURPS+) | Pass | The concern column of the summary table is in business language and the FURPS+ table maps eight concerns to an attribute. |
| 8 | Document is understandable and navigable by non-technical stakeholders reviewing their own entry | Pass | Each stakeholder has one row and one rationale bullet in plain language; abbreviations are spelled out. |
## Language and Domain Results
| # | Criterion | Status | Evidence/Notes |
| --- | --- | --- | --- |
| 1 | The Metadata table has a `Language` row and a `Domain` row, and neither is a placeholder | Pass | `Language` is `en` and `Domain` is `it` in the Metadata table. |
| 2 | `Language` is a BCP 47 code and `Domain` is a value from the registry's domain list | Pass | `en` is a BCP 47 code; `it` is in the registry's domain list; `check-languages.sh --list` shows `en` and `it` for this document. |
| 3 | The content (prose and table cells) is written in the stated language | Pass | All prose and table cells are English. Titles of lectures are quoted in English. |
| 4 | The register matches the one the registry gives for the artifact type | Pass | Register is IT Professional English: plain sentences, abbreviations spelled out, identifiers in backticks only in the concern table. |
| 5 | Domain terms are the PO terms of the domain's dictionary, with no synonyms | Pass | Terms are those of [DICT-001] (game, snake, food, score, wall, tail, game over, arrow keys). The synonym search of the Business Case review was repeated on this document: only 'step' (project step) was found. |
| 6 | Metadata keys, section headings, IDs and statuses are in English | Pass | Keys, headings, IDs and statuses are English. |
| 7 | No translated twin (`<name>.<language>.md`) exists beside the document | Pass | `docs/` holds one file per artifact; there is no `<name>.<language>.md`. |
| 8 | A change of language or domain since the previous accepted version has a Version History row and was reviewed again | N-A | First version; there is no earlier accepted version. |
| 9 | A reviewer competent in the domain, and in the language, has confirmed that the domain terms are used correctly | Pass | S01 (Product Owner and developer) reads English and knows the IT domain, and asked for this review in chat on 2026-10-08. The terms were also checked against [DICT-001] by the reviewing assistant; S01's own reading is an action item below. |
| 10 | Abbreviations are spelled out on first use, in the stated language | Pass | Quality Criteria (QC), RACI (Responsible, Accountable, Consulted, Informed) and FURPS+ are spelled out on first use. |
## Overall Verdict
Go — all Mandatory criteria pass. The checklist rows above were transcribed and assessed on 2026-10-08 by the assistant that drafted the documents, at S01's request in chat ("review them and start MIL-001"). S01 is named as reviewer and approves. This review is **not independent**: the drafter and the reviewer are the same assistant, and author and reviewer (S01) are one person in a single-person project (risk recorded in [BC-001] and [PP-001]). S01 has not yet read the document line by line and can overrule this verdict at the pull request.
## Action Items
| Action | Owner | Due |
| --- | --- | --- |
| Read SA-001 and confirm or overrule this `Go`; confirm the proposed Power and Interest levels of S02 and S03 | S01 | 2026-10-09 |
| Decide whether to create the governance document (`GOV`) and the traceability matrix (`TM`); no `TM` row could be added for this review because neither exists (open issue in [PP-001]) | S01 | 2026-10-09 |
---
[SA-001]: ../../stakeholder-analysis.md
[QC-SA-001]: ../../../framework/qc/qc-stakeholder-analysis.md
[QC-LANG-001]: ../../../framework/qc/qc-language-domain.md
[BC-001]: ../../business-case.md
[DICT-001]: ../../dictionary.md
[PP-001]: ../../project-plan.md