# Project Plan: Turtle Challenges
## Metadata
| Key | Value |
| --- | --- |
| ID | PP-001 |
| CrossReference | [BC-001], [SA-001], [MIL-001], [MIL-002], [MIL-003], [MIL-004] |
| Language | en |
| Domain | it |
## Version History
| Date | Status | Author | Reviewer | Change | Commit |
| --- | --- | --- | --- | --- | --- |
| 2026-10-07 | Deprecated | Jens Tirsvad Nielsen | S01 | Initial version | [4b3391b] |
| 2026-10-08 | Accepted | Jens Tirsvad Nielsen | S01 | Accepted by S01, the Product Owner<br>Reviews open issue updated | pending |
---
## Purpose
This plan schedules the four milestones that deliver the Turtle Challenges repository, one milestone per pull request, so that the work is complete by 2026-10-21, the end date in the constraints of [BC-001]. Each milestone is one `MIL-*` document with its own tasks; the tasks become issues on the git host.
## Planning Assumptions
- Week 1 starts 2026-10-07; the plan ends by 2026-10-21, per the Business Case constraint.
- Milestone length: three to four days, the length of one small pull request.
- S01 is the owner and the approving reviewer of every milestone (see [SA-001]); communication with S01 follows the cadence of the Stakeholder Analysis: at every milestone.
- The milestone dates are proposals; S01 confirms or moves them when reviewing this plan.
- One branch per milestone, named after it (`mil-001-project-foundation` and so on), opened as one pull request that closes its issues.
## Gateway Schedule
| Gateway | Document | Window | Decision date | Owner | Stories | Main deliverable | Milestone |
| --- | --- | --- | --- | --- | --- | --- | --- |
| Project Foundation | [MIL-001] | 2026-10-07 to 2026-10-10 | 2026-10-10 | S01 | none | `pyproject.toml`, `.gitignore`, package and test skeleton, `Doxyfile`, continuous integration, README, repository description and topics | [MIL-001 milestone] |
| Square and Dashed Line | [MIL-002] | 2026-10-11 to 2026-10-14 | 2026-10-14 | S01 | none | `Pen` protocol, `draw_square`, `draw_dashed_line`, fake turtle, tests, command line entry | [MIL-002 milestone] |
| Shapes and Random Color | [MIL-003] | 2026-10-15 to 2026-10-17 | 2026-10-17 | S01 | none | `random_color`, color palette, `draw_shape`, `draw_shapes`, tests | [MIL-003 milestone] |
| Random Walk and Spirograph | [MIL-004] | 2026-10-18 to 2026-10-21 | 2026-10-21 | S01 | none | `random_walk`, `draw_spirograph`, tests, final README | [MIL-004 milestone] |
```plantuml
@startgantt
Project starts 2026-10-07
[Project Foundation] starts 2026-10-07 and ends 2026-10-10
[Square and Dashed Line] starts 2026-10-11 and ends 2026-10-14
[Shapes and Random Color] starts 2026-10-15 and ends 2026-10-17
[Random Walk and Spirograph] starts 2026-10-18 and ends 2026-10-21
[Project Foundation Go/No-Go] happens 2026-10-10
[Square and Dashed Line Go/No-Go] happens 2026-10-14
[Shapes and Random Color Go/No-Go] happens 2026-10-17
[Random Walk and Spirograph Go/No-Go] happens 2026-10-21
@endgantt
```
## Scope Coverage
| Business Case scope item | Gateway |
| --- | --- |
| `src/`, `tests/`, `docs/` structure, `constants.py`, `pyproject.toml` | [MIL-001] |
| Python `.gitignore` | [MIL-001] |
| pytest, ruff and mypy set-up | [MIL-001]; each later milestone adds its tests |
| Continuous integration workflow | [MIL-001] |
| `Doxyfile` and the command to build the documentation | [MIL-001]; each later milestone keeps 0 warnings |
| README with set-up for Windows PowerShell, Linux Debian and macOS | [MIL-001] (first version), [MIL-004] (final) |
| Description and topics on the Gitea host and on GitHub | [MIL-001] |
| Challenge 1, draw a square | [MIL-002] |
| Challenge 2, draw a dashed line | [MIL-002] |
| Challenge 3, draw different shapes, and the `random_color` helper | [MIL-003] |
| Challenge 4, generate a random walk | [MIL-004] |
| Challenge 5, draw a spirograph | [MIL-004] |
## Dependencies
```
MIL-001 → MIL-002 → MIL-003 → MIL-004
```
Each milestone needs the previous one `Accepted` with a Go review. A No-Go returns the milestone for rework and every later window moves by the rework time; the end date 2026-10-21 has no slack beyond the windows, so a No-Go on any milestone means S01 re-plans the remaining dates instead of letting them slide unrecorded.
## Plan Risks
| Risk | Impact | Mitigation |
| --- | --- | --- |
| A milestone slips and the end date 2026-10-21 is missed | The deadline in [BC-001] is missed | Milestones are small; a No-Go triggers a re-plan with S01 and a new row in this document's Version History |
| The `Pen` protocol of [MIL-002] is wrong, and [MIL-003] and [MIL-004] build on it | Rework spreads over three milestones | Criteria 1, 2 and 5 of [MIL-002] test the protocol with the fake turtle before anything depends on it |
| The Gitea host has no Actions runner | Continuous integration cannot confirm the checks | Every milestone records the local results of pytest, ruff, mypy and Doxygen in its review; see the open issue below |
| A token in `.env` expires or lacks a scope | Issues or repository metadata cannot be created | S01 renews the token; the dry run of `sync-project.sh` shows the plan without a token |
## Open Issues
- **Python bound:** "Python greater than 3.13" is read as `>=3.13` (3.13.14 is installed on S01's machine). If a version newer than 3.13 is meant, `requires-python` and the continuous integration version change to 3.14 or later, which is not installed.
- **Dashed line length:** Turtle Challenge 2 says "a total of 50 segments", while the lecture's loop runs 15 times. The plan uses 50 dashes as a constant (`DASH_COUNT`) in `constants.py`; S01 confirms or sets 15.
- **README template:** the agreed README template (Requirements, Set up, Run, Run the tests, Continuous integration, Build the source documentation, Project layout, License) differs from `framework/templates/README-template.md`. `framework/scripts/check-readme.sh` would flag the difference if its opt-in check were enabled; the agreed template is followed. S01 decides whether the framework check stays off.
- **Use cases and user stories:** every task is a plain technical task. The program has one actor and one action (run a challenge), so no `UC` or `US` is written. S01 confirms.
- **Development tools:** ruff and mypy are added as development dependencies, beyond the pytest the brief names, because `QC-PY-001` requires a formatter, a linter and (optionally) a strict type check. They are not runtime dependencies.
- **Continuous integration host:** the workflow lives in `.github/workflows/ci.yml`, which GitHub Actions and Gitea Actions both read. Whether the Gitea host has a runner is not known.
- **Diagram:** the PlantUML Gantt chart is not rendered yet because no PlantUML server is configured (`render-diagrams.sh --server <url>`).
- **Reviews:** [BC-001], [SA-001], `DICT-001` and the four milestones were reviewed and ended in `Go` on 2026-10-07 (`RC-007` to `RC-013`, which re-review `RC-001` to `RC-006`); their Version History rows are `Accepted`. S01 accepted, in chat, that the author is also the reviewer, because the project has one person and no governance document exists. This plan has no checklist; S01 accepted it directly on 2026-10-08. S01 waived the plan-first gate in chat on 2026-10-07 for the first build, so the code of all four milestones was written before any document was reviewed; the waiver does not carry over to the next request. The code has not been reviewed against `QC-PY-001` yet.
- **GitHub:** issues are synced to the `origin` remote (the Gitea host) only; the GitHub mirror gets the description and topics but no milestones or issues.
---
[BC-001]: ./business-case.md
[SA-001]: ./stakeholder-analysis.md
[MIL-001]: ./milestones/mil-001-project-foundation.md
[MIL-002]: ./milestones/mil-002-square-and-dashed-line.md
[MIL-003]: ./milestones/mil-003-shapes-and-random-color.md
[MIL-004]: ./milestones/mil-004-random-walk-and-spirograph.md
[4b3391b]: https://git.tirsystem.com/Tirsvad-Udemy-100-days-of-code/018-turtle/commit/4b3391b22626b49aca06a7c265c1d0be93d1155d
[MIL-001 milestone]: https://git.tirsystem.com/Tirsvad-Udemy-100-days-of-code/018-turtle/milestone/70
[MIL-002 milestone]: https://git.tirsystem.com/Tirsvad-Udemy-100-days-of-code/018-turtle/milestone/71
[MIL-003 milestone]: https://git.tirsystem.com/Tirsvad-Udemy-100-days-of-code/018-turtle/milestone/72
[MIL-004 milestone]: https://git.tirsystem.com/Tirsvad-Udemy-100-days-of-code/018-turtle/milestone/73