# Stakeholder Analysis: Hirst Painting
|
|
|
|
## Metadata
|
|
| Key | Value |
|
|
| --- | --- |
|
|
| ID | SA-001 |
|
|
| CrossReference | [BC-001] |
|
|
| Language | en |
|
|
| Domain | it |
|
|
|
|
## Version History
|
|
| Date | Status | Author | Reviewer | Change | Commit |
|
|
| --- | --- | --- | --- | --- | --- |
|
|
| 2026-10-07 | Accepted | Jens Tirsvad Nielsen | S01 | Initial version | [b823d1f] |
|
|
|
|
---
|
|
|
|
## Purpose
|
|
|
|
This analysis identifies who has a stake in the Hirst painting program and
|
|
classifies each stakeholder by power and interest, so that other artifacts can
|
|
cite stable stakeholder IDs for ownership, review and RACI (responsible,
|
|
accountable, consulted, informed). It follows the power/interest grid and maps
|
|
each concern to a FURPS+ attribute (functionality, usability, reliability,
|
|
performance, supportability, plus further constraints). The project is a
|
|
one-person learning exercise, so the list has a single entry on purpose; a
|
|
stakeholder is added only when someone or something actually shapes the work.
|
|
|
|
## Stakeholder Summary Table
|
|
|
|
| ID | Name | Role/Title | Organization | Power Level | Interest Level | Quadrant | Primary Concern (Business Language) |
|
|
| --- | --- | --- | --- | --- | --- | --- | --- |
|
|
| S01 | Jens Tirsvad Nielsen | Product Owner, developer and reviewer | Tirsvad (individual) | HIGH | HIGH | Manage Closely | Finish the Day 18 exercise as a working, reviewed painting program that behaves as the lecture teaches, and learn from it without more process than the work needs |
|
|
|
|
## Power/Interest Classification Rationale
|
|
|
|
- **Manage Closely (S01):** S01 decides scope, accepts every artifact, owns
|
|
every phase and is the only person who works on the project, so power and
|
|
interest are both high. S01 is consulted at every review gate.
|
|
- **Other quadrants:** no stakeholder falls in Keep Satisfied, Keep Informed or
|
|
Monitor. The course lecture is the source of the required behaviour, but it
|
|
is a document, not a stakeholder: it is cited as the requirements source in
|
|
[BC-001] and takes no part in the project.
|
|
|
|
## Primary Concerns and FURPS+ Mapping
|
|
|
|
| ID | Concern | FURPS+ attribute |
|
|
| --- | --- | --- |
|
|
| S01 | The program draws the painting correctly and as the lecture teaches: 100 dots, right size and spacing, palette without white, random colours | Functionality |
|
|
| S01 | The result looks clean and the window stays open until a click | Usability |
|
|
| S01 | The drawing finishes quickly enough to not be tedious | Performance |
|
|
| S01 | The code is readable and passes the Python checklist | Supportability |
|
|
| S01 | The process stays proportionate to a one-script project | Supportability |
|
|
|
|
## Communication Requirements
|
|
|
|
| ID | Channel | Frequency | Deliverable | Phase / Milestone |
|
|
| --- | --- | --- | --- | --- |
|
|
| S01 | Chat with the assistant, working-tree review | At each review gate: Business Case and Stakeholder Analysis, Project Plan, each milestone, the code | Documents in `docs/`, review records `RC-*`, dry-run output of `sync-project.sh` | Every review gate before the next step starts |
|
|
| S01 | Pull request on the git host | Once, when S01 asks for it | Pull request closing the completed issues | Code review before the pull request |
|
|
|
|
## Conflicting Interests and Mitigations
|
|
|
|
With one stakeholder there is no conflict between people; the conflicts below
|
|
are tensions inside S01's own interests, and one process conflict.
|
|
|
|
| Conflict | Stakeholders | Mitigation |
|
|
| --- | --- | --- |
|
|
| S01 wants to practise the full framework workflow but also to finish a small exercise quickly | S01 | Two phases only, plain technical tasks, no use cases or design artifacts; the Business Case names this as a risk and as Out of Scope |
|
|
| S01 may want to change values from the lecture (dot size, spacing, thresholds) while the Business Case fixes them as targets | S01 | S01 owns the decision; a change is made through a new Version History row of [BC-001] and a re-review |
|
|
| The framework asks for a reviewer who is not the author, but S01 is the only person on the project | S01 | S01 accepted a documented self-review on 2026-10-07, recorded in the review records of [BC-001] and this document; the assistant never marks a document `Accepted` itself |
|
|
|
|
## Traceability Analysis
|
|
|
|
### Business Goal Alignment
|
|
|
|
| Stakeholder | Concern | Business Case objective |
|
|
| --- | --- | --- |
|
|
| S01 | Correct painting, as the lecture teaches | O1, O2, O3 of [BC-001] |
|
|
| S01 | Clean, quick result | O4 of [BC-001] |
|
|
| S01 | Reviewed, proportionate delivery | O5 of [BC-001] |
|
|
|
|
Actor mapping: S01 is the only actor, as the person who runs the program and
|
|
clicks the window to close it. The program has no other user, so no use cases
|
|
are modelled; this is recorded as out of scope in [BC-001].
|
|
|
|
## Sign-Off
|
|
|
|
Pending. Sign-off is recorded by the review record (`RC-*`) of this document.
|
|
The assistant does not mark the document `Accepted`.
|
|
|
|
---
|
|
|
|
[BC-001]: ./business-case.md
|
|
[b823d1f]: https://git.tirsystem.com/Tirsvad-Udemy-100-days-of-code/018-hirst-painting/commit/b823d1f405ebac6b0198605edd9d802518529725
|