Project Plan: Hirst Painting

Metadata

Key Value
ID PP-001
CrossReference BC-001, SA-001, MIL-001, MIL-002
Language en
Domain it

Version History

Date Status Author Reviewer Change Commit
2026-10-07 Deprecated Jens Tirsvad Nielsen S01 Initial version b823d1f
2026-10-08 Accepted Jens Tirsvad Nielsen S01 Recorded the Go decisions of MIL-001 and MIL-002
Closed the reference-image open issue
a6b17d3

Purpose

This plan schedules the two phases of the Hirst painting project, the colour palette and the spot painting, inside the one-week limit that BC-001 sets (2026-10-07 to 2026-10-14). Each phase is a gateway with its own milestone document, and each gateway ends with a Go/No-Go decision by S01.

Planning Assumptions

  • Week 1 starts 2026-10-07; the plan ends by 2026-10-14, per the Business Case assumption confirmed by S01.
  • The baseline documents (BC-001, SA-001 and their review records) are finished on 2026-10-07, before the first phase starts.
  • Phase length: two to five days, because the work is one small script. The palette phase is shorter because it is the smaller of the two.
  • S01 owns both phases and takes both Go/No-Go decisions; S01 is the only stakeholder in SA-001, so communication follows the review gates in that document.
  • No user stories exist: the program has no user interaction beyond the exit click, so the Stories column is empty.

Gateway Schedule

Gateway Document Window Decision date Owner Stories Main deliverable Milestone
Colour palette MIL-001 2026-10-07 to 2026-10-09 2026-10-09 S01 none Palette function that returns the reference image's colours without white shades MIL-001 milestone
Spot painting MIL-002 2026-10-10 to 2026-10-14 2026-10-14 S01 none Program that draws the 10 by 10 painting and meets SC1 to SC7 of BC-001 MIL-002 milestone
@startgantt
Project starts 2026-10-07
[Colour palette] starts 2026-10-07 and ends 2026-10-09
[Colour palette Go/No-Go] happens 2026-10-09
[Spot painting] starts 2026-10-10 and ends 2026-10-14
[Spot painting Go/No-Go] happens 2026-10-14
@endgantt

Scope Coverage

Business Case scope item Gateway
One Python program using turtle, random and colorgram MIL-001 (colorgram part), MIL-002 (turtle and random part)
Palette extracted from one reference image, white shades removed MIL-001
Drawing the 10 by 10 dot grid: size, spacing, row change, heading MIL-002
Screen handling: exitonclick, hidden turtle, pen up, drawing speed MIL-002
Framework documents and review records for the plan-first workflow Finished before the first gateway (BC-001, SA-001, this plan, MIL-001, MIL-002 and their reviews); the review of each phase's code is a task in that phase

Dependencies

Baseline documents → [MIL-001] Colour palette → [MIL-002] Spot painting

MIL-002 needs the palette function from MIL-001. A No-Go on MIL-001 moves the start of MIL-002 by the days needed to rework and re-review; the one-week limit then has no slack, so S01 decides whether to extend it.

Plan Risks

Risk Impact Mitigation
The reference image is not supplied before the palette phase starts MIL-001 cannot start its extraction task; the window of two to three days is lost The tasks that do not need the image (toolchain check, white filter and its tests) come first; S01 decides on another image if this one stays unavailable
A No-Go on the palette phase MIL-002 starts late and the one-week limit is missed The palette phase is the smaller one and ends 2026-10-09, leaving five days for the painting phase
Review effort is large compared with the code Time goes to documents instead of the program Two phases, plain tasks, no use cases or design artifacts, as set out in BC-001
The Project Plan has no quality checklist The plan is accepted on S01's judgement alone S01 checks the plan against the one-week limit of BC-001 and the Go/No-Go criteria of both milestones

Open Issues

  • Reference image: resolved. S01 supplied assets/20260524_132700.jpg on 2026-10-07, which completed task 4 of MIL-001.
  • Project Plan review: the Project Plan has no quality checklist yet, so it is Accepted when S01 says so in chat (done on 2026-10-07, and again on 2026-10-08 for the gateway decisions); no review record is written for it.
  • Milestone links: sync-project.sh --apply ran on 2026-10-07 and created the two Milestones and issues #1 to #13 on the git host; the Milestone column links to them.

Gateway Decisions

The Go/No-Go decision of each gateway, taken by its owner (S01) in chat and recorded here by the assistant. The Decision date in the Gateway Schedule is the planned date; the date below is the actual one.

Gateway Document Decision Decided by Decision date Planned date Basis
Colour palette MIL-001 Go S01 2026-10-08 2026-10-09 All five Go criteria met: imports and window, 30 colours, no white shade, 18 tests passing, code review RC-005 with verdict Go. Pull request PR 14 merged; Milestone closed on the git host
Spot painting MIL-002 Go S01 2026-10-08 2026-10-14 All six Go criteria met: 100 dots in 10 rows of 10, size 20 and 50 apart, colours from the palette, clean result with the window open until a click, drawn in 0.35 seconds, code review RC-006 with verdict Go. Pull request PR 16 merged; Milestone closed on the git host

Both decisions came before the planned dates because every Go criterion was already met. The two open decisions on RC-006 (the display requirement of the tests and the pale palette colours) did not block either one.