Project Plan: Hirst Painting
Metadata
Version History
| Date |
Status |
Author |
Reviewer |
Change |
Commit |
| 2026-10-07 |
Deprecated |
Jens Tirsvad Nielsen |
S01 |
Initial version |
b823d1f |
| 2026-10-08 |
Accepted |
Jens Tirsvad Nielsen |
S01 |
Recorded the Go decisions of MIL-001 and MIL-002 Closed the reference-image open issue |
a6b17d3 |
Purpose
This plan schedules the two phases of the Hirst painting project, the colour
palette and the spot painting, inside the one-week limit that BC-001 sets
(2026-10-07 to 2026-10-14). Each phase is a gateway with its own milestone
document, and each gateway ends with a Go/No-Go decision by S01.
Planning Assumptions
- Week 1 starts 2026-10-07; the plan ends by 2026-10-14, per the Business Case assumption confirmed by S01.
- The baseline documents (BC-001, SA-001 and their review records) are finished on 2026-10-07, before the first phase starts.
- Phase length: two to five days, because the work is one small script. The palette phase is shorter because it is the smaller of the two.
- S01 owns both phases and takes both Go/No-Go decisions; S01 is the only stakeholder in SA-001, so communication follows the review gates in that document.
- No user stories exist: the program has no user interaction beyond the exit click, so the Stories column is empty.
Gateway Schedule
| Gateway |
Document |
Window |
Decision date |
Owner |
Stories |
Main deliverable |
Milestone |
| Colour palette |
MIL-001 |
2026-10-07 to 2026-10-09 |
2026-10-09 |
S01 |
none |
Palette function that returns the reference image's colours without white shades |
MIL-001 milestone |
| Spot painting |
MIL-002 |
2026-10-10 to 2026-10-14 |
2026-10-14 |
S01 |
none |
Program that draws the 10 by 10 painting and meets SC1 to SC7 of BC-001 |
MIL-002 milestone |
Scope Coverage
| Business Case scope item |
Gateway |
One Python program using turtle, random and colorgram |
MIL-001 (colorgram part), MIL-002 (turtle and random part) |
| Palette extracted from one reference image, white shades removed |
MIL-001 |
| Drawing the 10 by 10 dot grid: size, spacing, row change, heading |
MIL-002 |
Screen handling: exitonclick, hidden turtle, pen up, drawing speed |
MIL-002 |
| Framework documents and review records for the plan-first workflow |
Finished before the first gateway (BC-001, SA-001, this plan, MIL-001, MIL-002 and their reviews); the review of each phase's code is a task in that phase |
Dependencies
MIL-002 needs the palette function from MIL-001. A No-Go on MIL-001 moves
the start of MIL-002 by the days needed to rework and re-review; the
one-week limit then has no slack, so S01 decides whether to extend it.
Plan Risks
| Risk |
Impact |
Mitigation |
| The reference image is not supplied before the palette phase starts |
MIL-001 cannot start its extraction task; the window of two to three days is lost |
The tasks that do not need the image (toolchain check, white filter and its tests) come first; S01 decides on another image if this one stays unavailable |
| A No-Go on the palette phase |
MIL-002 starts late and the one-week limit is missed |
The palette phase is the smaller one and ends 2026-10-09, leaving five days for the painting phase |
| Review effort is large compared with the code |
Time goes to documents instead of the program |
Two phases, plain tasks, no use cases or design artifacts, as set out in BC-001 |
| The Project Plan has no quality checklist |
The plan is accepted on S01's judgement alone |
S01 checks the plan against the one-week limit of BC-001 and the Go/No-Go criteria of both milestones |
Open Issues
- Reference image: resolved. S01 supplied
assets/20260524_132700.jpg on 2026-10-07, which completed task 4 of MIL-001.
- Project Plan review: the Project Plan has no quality checklist yet, so it is
Accepted when S01 says so in chat (done on 2026-10-07, and again on 2026-10-08 for the gateway decisions); no review record is written for it.
- Milestone links:
sync-project.sh --apply ran on 2026-10-07 and created the two Milestones and issues #1 to #13 on the git host; the Milestone column links to them.
Gateway Decisions
The Go/No-Go decision of each gateway, taken by its owner (S01) in chat and recorded here by the assistant. The Decision date in the Gateway Schedule is the planned date; the date below is the actual one.
| Gateway |
Document |
Decision |
Decided by |
Decision date |
Planned date |
Basis |
| Colour palette |
MIL-001 |
Go |
S01 |
2026-10-08 |
2026-10-09 |
All five Go criteria met: imports and window, 30 colours, no white shade, 18 tests passing, code review RC-005 with verdict Go. Pull request PR 14 merged; Milestone closed on the git host |
| Spot painting |
MIL-002 |
Go |
S01 |
2026-10-08 |
2026-10-14 |
All six Go criteria met: 100 dots in 10 rows of 10, size 20 and 50 apart, colours from the palette, clean result with the window open until a click, drawn in 0.35 seconds, code review RC-006 with verdict Go. Pull request PR 16 merged; Milestone closed on the git host |
Both decisions came before the planned dates because every Go criterion was already met. The two open decisions on RC-006 (the display requirement of the tests and the pale palette colours) did not block either one.