Files
016-pretty-table/.agents/skills/artifact/templates/PP.md
T
Tirsvad b0a7414204 Add Pretty Table project: plan, accepted documents and code
Business Case, Stakeholder Analysis, Project Plan and milestone MIL-001
with review records RC-001 to RC-003, then the Python project: PrettyTable
Pokemon table, constants, pytest tests, pyproject.toml, Doxyfile, CI
workflow and README.

Task: MIL-001#1
Task: MIL-001#2
Task: MIL-001#3
Task: MIL-001#4
Task: MIL-001#5
Task: MIL-001#6
Task: MIL-001#7
Task: MIL-001#8
2026-10-07 12:02:59 +08:00

64 lines
1.3 KiB
Markdown

# @TITLE@
## Metadata
| Key | Value |
| --- | --- |
| ID | @ID@ |
| CrossReference | @CROSSREF@ |
| Language | @LANGUAGE@ |
| Domain | @DOMAIN@ |
## Version History
| Date | Status | Author | Reviewer | Change | Commit |
| --- | --- | --- | --- | --- | --- |
| @DATE@ | Proposed | @AUTHOR@ | <reviewer S-ID> | Initial version | pending |
---
## Purpose
<what this plan schedules, and over what constraint>
## Planning Assumptions
- Week 1 starts <date>; the plan ends by <date>, per the Business Case constraint.
- Phase length: <e.g. two weeks>.
## Gateway Schedule
| Gateway | Document | Window | Decision date | Owner | Stories | Main deliverable | Milestone |
| --- | --- | --- | --- | --- | --- | --- | --- |
| <name> | [MIL-<n>] | <dates> | <date> | <S-ID> | <US-…> | <deliverable> | <link once synced> |
```plantuml
@startgantt
Project starts <start YYYY-MM-DD>
[Phase 1] starts <start YYYY-MM-DD> and ends <end YYYY-MM-DD>
[Phase 1 Go/No-Go] happens <date YYYY-MM-DD>
@endgantt
```
## Scope Coverage
| Business Case scope item | Gateway |
| --- | --- |
## Dependencies
```
<phase 1> → <phase 2> → ...
```
## Plan Risks
| Risk | Impact | Mitigation |
| --- | --- | --- |
## Open Issues
- <unresolved item>
---