CI / test (push) Successful in 54s
Plan project and set up Phase 1 skeleton
Add the framework submodule and the accepted planning documents:
Business Case, Stakeholder Analysis, Project Plan, three milestones,
review records RC-001 to RC-006 and the traceability matrix.

Set up the project skeleton for MIL-001: pyproject.toml (Python
>=3.13, no runtime dependencies, pytest/ruff/mypy as dev extra),
 src/coffee_machine/constants.py, a constants consistency test,
 Doxyfile and a CI workflow that runs ruff, mypy and pytest.

Task: MIL-001#1
Task: MIL-001#2
Task: MIL-001#3
Task: MIL-001#4
Task: MIL-001#5
Closes #1
Closes #2
Closes #3
Closes #4
Closes #5
2026-10-07 10:43:22 +08:00

3.3 KiB

Project Plan: OOP Coffee Machine

Metadata

Key Value
ID PP-001
CrossReference BC-001, SA-001, MIL-001, MIL-002, MIL-003
Language en
Domain it

Version History

Date Status Author Reviewer Change Commit
2026-10-07 Deprecated Jens Tirsvad Nielsen S01 Initial version pending
2026-10-07 Accepted Jens Tirsvad Nielsen S01 Accepted after RC-006 (Go) pending

Purpose

Schedules the three phases that deliver the coffee machine repository, as required by BC-001, with the communication cadence of SA-001.

Planning Assumptions

  • Start date 2026-10-07; one phase per week or less, each ending in a pull request.
  • S01 is owner and reviewer of every phase; S02 and S03 are informed through the README.
  • Nothing under src/ or tests/ is written until the milestones are Accepted with a Go review.

Gateway Schedule

Gateway Document Window Decision date Owner Stories Main deliverable Milestone
Phase 1: Project Setup MIL-001 2026-10-07 to 2026-10-09 2026-10-09 S01 None Skeleton, pyproject.toml, Doxyfile, CI
Phase 2: Coffee Machine Program MIL-002 2026-10-10 to 2026-10-14 2026-10-14 S01 None Menu, CoffeeMaker, MoneyMachine, main loop, tests
Phase 3: Documentation and Publication MIL-003 2026-10-15 to 2026-10-16 2026-10-16 S01 None README, Doxygen docs, repository description and topics

Timeline diagram

@startgantt
Project starts 2026-10-07
[Phase 1: Project Setup] starts 2026-10-07 and ends 2026-10-09
[Phase 2: Coffee Machine Program] starts 2026-10-10 and ends 2026-10-14
[Phase 3: Documentation and Publication] starts 2026-10-15 and ends 2026-10-16
[Phase 1: Project Setup] -> [Phase 2: Coffee Machine Program]
[Phase 2: Coffee Machine Program] -> [Phase 3: Documentation and Publication]
@endgantt

Scope Coverage

Business Case scope item Gateway
Package, tests, pyproject.toml, .gitignore, constants.py, Doxyfile MIL-001
Coffee machine program and tests MIL-002
README, Doxygen build MIL-003
Repository description and topics MIL-003

Dependencies

MIL-001 precedes MIL-002, which precedes MIL-003. A No-Go on a phase moves every later date by the rework time.

Plan Risks

Risk Impact Mitigation
Review of each document delays the next phase Medium S01 reviews in the same session as the draft
The git host token cannot set topics through the API Low Set the description and topics by hand in the web UI

Open Issues

  • Dates are proposals; S01 confirms or changes them.
  • Tasks are all plain tasks: the course supplies the design, so no use case or user story is modelled. S01 may ask for a use case "User orders a drink".
  • PP has no QC checklist yet; the plan is validated against the Go / No-Go criteria of each milestone.
  • Which remote receives the repository description and topics (git.tirsystem.com, GitHub mirror, or both) is for S01 to confirm; both remotes exist.