Fills the Milestone column of the Gateway Schedule in PP-001 with links to the Gitea milestones 49, 50 and 51, as the plan prescribes after sync-project.sh --apply. This is a content update, so it adds no Version History row.
Notes for the reviewer
Documentation only; no code changes.
Milestones 49 and 50 are still open on Gitea although all their issues are closed. Milestone 51 closes its issues when PR #18 (README) merges. Close the milestones once all issues are closed.
No issue closed: this change only adds links to existing milestones.
## Summary
Fills the `Milestone` column of the Gateway Schedule in PP-001 with links to the Gitea milestones 49, 50 and 51, as the plan prescribes after `sync-project.sh --apply`. This is a content update, so it adds no Version History row.
## Notes for the reviewer
- Documentation only; no code changes.
- Milestones 49 and 50 are still open on Gitea although all their issues are closed. Milestone 51 closes its issues when PR #18 (README) merges. Close the milestones once all issues are closed.
No issue closed: this change only adds links to existing milestones.
Blocking a user prevents them from interacting with repositories, such as opening or commenting on pull requests or issues. Learn more about blocking a user.
Summary
Fills the
Milestonecolumn of the Gateway Schedule in PP-001 with links to the Gitea milestones 49, 50 and 51, as the plan prescribes aftersync-project.sh --apply. This is a content update, so it adds no Version History row.Notes for the reviewer
No issue closed: this change only adds links to existing milestones.