| 1 |
Purpose states what is scheduled and over what constraint |
Pass |
Fixed in v3: it said "three phases" and "short assignment timeline"; it now says four phases and the one-week duration in [BC-001]. |
| 2 |
Planning assumptions give the start date and phase length, consistent with the Business Case duration |
Pass |
Start 2026-10-05, end 2026-10-12, as in the Business Case duration constraint. Fixed in v3: "one branch and one pull request per phase" did not match what happened. |
| 3 |
Gateway Schedule has one row per MIL-* document, with its Milestone link once synced |
Pass |
Four rows for MIL-001 to MIL-004; Milestones 40, 41, 42 and 48 are linked. |
| 4 |
Timeline diagram has one bar per phase and a marker per Go/No-Go decision |
Pass |
Four bars and four markers. The diagram was not rendered: no PlantUML server is configured. |
| 5 |
Scope Coverage maps every Business Case scope item to a gateway |
Pass |
All six In Scope items of BC-001 v4 map to MIL-001 to MIL-004 or to planning. |
| 6 |
Dependencies state the gateway order and what a No-Go does to later dates |
Pass |
Fixed in v3: the chain said MIL-004 follows MIL-003 but the windows overlap. The text now says MIL-004 may start once the MIL-003 tests are merged. |
| 7 |
Plan risks are specific to the plan and each has a mitigation |
Pass |
Fixed in v3: the "README template not supplied" risk was resolved and was removed. Two risks remain, each with a mitigation. |
| 8 |
Open Issues lists only unresolved items |
Pass |
Fixed in v3: the README template and the Python version reading were resolved (README written; BC-001 v4 states the reading). One open item remains: the optional use case. |
| 9 |
CrossReference cites the Business Case, the Stakeholder Analysis and every MIL-* document, and the links are defined |
Pass |
BC-001, SA-001 and MIL-001 to MIL-004 are cited and defined. |
| 10 |
Windows and decision dates agree with each MIL-* Target Date and the Business Case duration |
Pass |
Decision dates 2026-10-07, 10-10, 10-12, 10-12 equal the Target Dates; all lie inside 2026-10-05 to 2026-10-12. |