Tirsvad a1ff73580f Accept BC, SA, PP and MIL-001 after review
Review BC-001, SA-001, PP-001 and MIL-001 and record the results as
RC-001 to RC-004. All four verdicts are Go, so their Version History
rows become Accepted and the previous rows Deprecated. MIL-002 to
MIL-004 stay Proposed.

BC-001 failed criterion 1 (cost-benefit not justified as qualitative).
Add the justification and a target-completion constraint (2026-10-14)
that PP-001 and MIL-001 are checked against.

Add the Traceability Matrix (TM-001) and register RC and TM in the
artifact registry. PP has no QC checklist, so RC-003 checks the plan
against BC-001 and the milestones instead. Author and reviewer are
both S01, a deviation noted in each record.

Refs #5
2026-10-04 23:23:12 +08:00

45 lines
1.8 KiB
Markdown
Raw Blame History

This file contains ambiguous Unicode characters
This file contains Unicode characters that might be confused with other characters. If you think that this is intentional, you can safely ignore this warning. Use the Escape button to reveal them.
# SQA Review Record: Project Plan
## Metadata
| Key | Value |
| --- | --- |
| ID | RC-003 |
| CrossReference | [PP-001] |
## Version History
| Date | Status | Author | Reviewer | Change | Commit |
| --- | --- | --- | --- | --- | --- |
| 2026-10-04 | Accepted | Jens Tirsvad Nielsen | S01 | Initial version | pending |
---
## Artifact Under Review
- Instance reviewed: [PP-001]
- Checklist used: none exists for this type (`PP` has no QC checklist); criteria below follow `references/PP.md` "Validating".
## Checklist Results
| # | Criterion | Status | Evidence/Notes |
| --- | --- | --- | --- |
| 1 | Every MIL-* gateway is scheduled | Pass | MIL-001 to MIL-004 listed with window, decision date and owner. |
| 2 | Schedule is consistent with the Business Case constraint | Pass | Ends 2026-10-14, matching the target-date constraint added to BC-001. |
| 3 | Gateway Schedule, Gantt, Scope Coverage, Dependencies, Plan Risks and Open Issues sections are present | Pass | All required sections present. |
| 4 | Each phase links to its synced Milestone | Pass | Milestones 36–39 linked. |
| 5 | Every Business Case scope item maps to a gateway | Pass | Scope Coverage table. |
## Overall Verdict
Go — no QC checklist exists for PP, so the plan was checked against BC-001 and the MIL-* documents. Open issues (README template, Python version, dates) remain listed in the plan. Reviewer and author are both S01: the project has a single participant, so the framework's author/reviewer separation cannot be met. S01 accepted this deviation when requesting acceptance (2026-10-04).
## Action Items
| Action | Owner | Due |
| --- | --- | --- |
| Provide README template before MIL-004 task 1 | S01 | 2026-10-13 |
| Confirm requires-python (>=3.13 or 3.14+) | S01 | 2026-10-06 |
---
[PP-001]: ../../project-plan.md