Tirsvad a1ff73580f Accept BC, SA, PP and MIL-001 after review
Review BC-001, SA-001, PP-001 and MIL-001 and record the results as
RC-001 to RC-004. All four verdicts are Go, so their Version History
rows become Accepted and the previous rows Deprecated. MIL-002 to
MIL-004 stay Proposed.

BC-001 failed criterion 1 (cost-benefit not justified as qualitative).
Add the justification and a target-completion constraint (2026-10-14)
that PP-001 and MIL-001 are checked against.

Add the Traceability Matrix (TM-001) and register RC and TM in the
artifact registry. PP has no QC checklist, so RC-003 checks the plan
against BC-001 and the milestones instead. Author and reviewer are
both S01, a deviation noted in each record.

Refs #5
2026-10-04 23:23:12 +08:00

48 lines
1.8 KiB
Markdown
Raw Blame History

This file contains ambiguous Unicode characters
This file contains Unicode characters that might be confused with other characters. If you think that this is intentional, you can safely ignore this warning. Use the Escape button to reveal them.
# SQA Review Record: Stakeholder Analysis
## Metadata
| Key | Value |
| --- | --- |
| ID | RC-002 |
| CrossReference | [SA-001], [QC-SA-001] |
## Version History
| Date | Status | Author | Reviewer | Change | Commit |
| --- | --- | --- | --- | --- | --- |
| 2026-10-04 | Accepted | Jens Tirsvad Nielsen | S01 | Initial version | pending |
---
## Artifact Under Review
- Instance reviewed: [SA-001]
- Checklist used: [QC-SA-001]
## Checklist Results
| # | Criterion | Status | Evidence/Notes |
| --- | --- | --- | --- |
| 1 | Power/Interest grid is filled for every stakeholder | Pass | S01–S03 all classified. |
| 2 | Each stakeholder has a unique, stable ID | Pass | S01, S02, S03. |
| 3 | Roles and organizational context defined with explicit Power and Interest levels | Pass | Summary table. |
| 4 | Communication needs mapped to phases or milestones (Optional) | Pass | Communication Requirements table cites MIL-001 to MIL-004. |
| 5 | Conflicting interests identified with mitigation | Pass | One conflict (tooling versus simple repository), mitigated. |
| 6 | Stakeholder concerns traced to Business Case objectives | Pass | Business Goal Alignment table cites O1–O5. |
| 7 | Concerns expressed in business language and FURPS+ (Optional) | Pass | FURPS+ mapping table. |
| 8 | Understandable by non-technical stakeholders (Optional) | Pass | Plain language, short document. |
## Overall Verdict
Go — all criteria pass. Reviewer and author are both S01: the project has a single participant, so the framework's author/reviewer separation cannot be met. S01 accepted this deviation when requesting acceptance (2026-10-04).
## Action Items
| Action | Owner | Due |
| --- | --- | --- |
| None | — | — |
---
[SA-001]: ../../stakeholder-analysis.md
[QC-SA-001]: ../../../framework/qc/qc-stakeholder-analysis.md