# SQA Review Record: MIL-001 Project setup
## Metadata
| Key | Value |
| --- | --- |
| ID | RC-004 |
| CrossReference | [MIL-001], [QC-MIL-001] |
## Version History
| Date | Status | Author | Reviewer | Change | Commit |
| --- | --- | --- | --- | --- | --- |
| 2026-10-04 | Accepted | Jens Tirsvad Nielsen | S01 | Initial version | [a1ff735] |
---
## Artifact Under Review
- Instance reviewed: [MIL-001]
- Checklist used: [QC-MIL-001]
## Checklist Results
| # | Criterion | Status | Evidence/Notes |
| --- | --- | --- | --- |
| 1 | A concrete deliverable is defined for every gate | Pass | Config files, skeleton, passing smoke test, repository metadata. |
| 2 | Explicit Go/No-Go criteria are stated for each gate | Pass | Six objectively checkable criteria. |
| 3 | Dependencies on other milestones are explicitly mapped (Optional) | Pass | First phase; stated as none. |
| 4 | Each milestone is traceable to a Business Case objective or KPI | Pass | O2, O4, O5. |
| 5 | Milestone owner and approving reviewer are identified | Pass | S01 and S01. |
| 6 | Milestone has a target date consistent with project constraints | Pass | 2026-10-06, inside the 2026-10-14 constraint in BC-001. |
## Overall Verdict
Go — all criteria pass. MIL-002 to MIL-004 stay Proposed. Reviewer and author are both S01: the project has a single participant, so the framework's author/reviewer separation cannot be met. S01 accepted this deviation when requesting acceptance (2026-10-04).
## Action Items
| Action | Owner | Due |
| --- | --- | --- |
| Confirm requires-python before issue #1 starts | S01 | 2026-10-06 |
---
[MIL-001]: ../../milestones/mil-001-project-setup.md
[QC-MIL-001]: ../../../framework/qc/qc-milestones-gateways.md