Review Record: MIL-001 Stabilise the metadata sync

Metadata

Key Value
ID RC-003
CrossReference MIL-001, QC-MIL-001

Version History

Date Status Author Reviewer Change Commit
2026-10-10 Accepted Jens Tirsvad Nielsen S05 Initial version c017c06

Artifact Under Review

Checklist Results

# Criterion Status Evidence/Notes
1 A concrete deliverable is defined for every gate Pass Deliverable section: one canonical workflow, passing validation and tests, an accurate README and a manual run.
2 Explicit Go/No-Go criteria are stated for each gate Pass Five criteria, each with an objectively checkable Go and No-Go column.
3 Dependencies on other milestones are explicitly mapped Pass Dependencies: none, first milestone.
4 Each milestone is traceable to a Business Case objective or KPI Pass Traceability maps MIL-001 to O1 and O2 of BC-001.
5 Milestone owner and approving reviewer are identified Pass Owner S05 and approving reviewer S01.
6 Milestone has a defined target date consistent with project constraints Pass Target date 2026-10-17, marked proposed; the Business Case sets no deadline, so there is nothing to contradict.

Overall Verdict

Go — all six criteria pass. S01 gave the Go in chat on 2026-10-10 for the amendment of the task 1 decision (zero GitHub mirrors is a successful skip) and the matching task 5 test scope. Go / No-Go criterion 5 (manual run on Gitea) is still open as task 7 (issue 7) and is not changed by this amendment. The author and the approving reviewer are the same person (S01); the independent S05 review is recorded in RC-001 and applies here too.

Action Items

Action Owner Due
Run the manual workflow_dispatch check on Gitea for the amended behaviour: a repository with a GitHub mirror and one without (task 7) S05 2026-10-17