# Review Record: MIL-005 Wiki and translations
|
|
|
|
## Metadata
|
|
| Key | Value |
|
|
| --- | --- |
|
|
| ID | RC-010 |
|
|
| CrossReference | [MIL-005], [QC-MIL-001] |
|
|
|
|
## Version History
|
|
| Date | Status | Author | Reviewer | Change | Commit |
|
|
| --- | --- | --- | --- | --- | --- |
|
|
| 2026-10-10 | Accepted | Jens Tirsvad Nielsen | S01 | Initial version | pending |
|
|
|
|
---
|
|
|
|
## Artifact Under Review
|
|
|
|
- Instance reviewed: [MIL-005]
|
|
- Checklist used: [QC-MIL-001]
|
|
|
|
## Checklist Results
|
|
|
|
| # | Criterion | Status | Evidence/Notes |
|
|
| --- | --- | --- | --- |
|
|
| 1 | A concrete deliverable is defined for every gate | Pass | Fifteen wiki pages, a generation script and the `AGENTS.md` rule. |
|
|
| 2 | Explicit Go/No-Go criteria are stated for each gate | Pass | Five criteria, each with a checkable Go and No-Go column. |
|
|
| 3 | Dependencies on other milestones are explicitly mapped | Pass | Depends on MIL-002, with the reason. |
|
|
| 4 | Each milestone is traceable to a Business Case objective or KPI | Pass | Traceability maps MIL-005 to O3 of BC-001. |
|
|
| 5 | Milestone owner and approving reviewer are identified | Pass | Owner S05, approving reviewer S01. |
|
|
| 6 | Milestone has a defined target date consistent with project constraints | Pass | 2026-12-12, marked proposed; the Business Case sets no deadline. |
|
|
|
|
## Overall Verdict
|
|
|
|
Go - all six criteria pass. S01 gave the Go in chat on 2026-10-10. Accepting the milestone is what unlocks its tasks under the plan-first gate; the issues are still to be created with `sync-project.sh --apply`. The author and S01 are the same person, so the independent S05 review recorded in RC-001 is still open.
|
|
|
|
## Action Items
|
|
|
|
| Action | Owner | Due |
|
|
| --- | --- | --- |
|
|
| Decide how the agent publishes to the wiki repository (task 2): push with a token or prepare changes for review | S01 | 2026-10-17 |
|
|
| Confirm the proposed target date with S01 and S05 | S05 | 2026-10-17 |
|
|
|
|
---
|
|
|
|