Review Record: MIL-003

Metadata

Key Value
ID RC-006
CrossReference MIL-003, QC-MIL-001

Version History

Date Status Author Reviewer Change Commit
2026-10-10 Proposed Jens Tirsvad Nielsen S05 Initial version aa3f088

Artifact Under Review

Checklist Results

# Criterion Status Evidence/Notes
1 A concrete deliverable is defined for every gate Pass Deliverable: a reusable quality-check workflow used by one other repository, and a results guide.
2 Explicit Go/No-Go criteria are stated for each gate Pass Four criteria, each with an objectively checkable Go and No-Go column.
3 Dependencies on other milestones are explicitly mapped Pass Dependencies: depends on MIL-002, with the reason stated.
4 Each milestone is traceable to a Business Case objective or KPI Pass Traceability maps MIL-003 to O4 of BC-001.
5 Milestone owner and approving reviewer are identified Pass Owner S05 and approving reviewer S01.
6 Milestone has a defined target date consistent with project constraints Pass Target date 2026-11-14, marked proposed; the Business Case sets no deadline, so nothing contradicts it.

Overall Verdict

Go — all six criteria pass. Retrospective review prepared 2026-10-10 at the request of S01; the instance has been Accepted since 2026-10-03 and this record confirms it against the checklist. The author and the approving reviewer are the same person (S01); independent review by S05 is recorded in RC-001 and applies here too.

Action Items

Action Owner Due
Confirm the proposed target date with S01 and S05 (the date is still marked proposed) S05 2026-10-17