# ADR-0002: S01 approves as stand-in for other reviewers
|
|
|
|
## Metadata
|
|
| Key | Value |
|
|
| --- | --- |
|
|
| ID | ADR-0002 |
|
|
| CrossReference | [SA-001], [RC-001] |
|
|
|
|
## Version History
|
|
| Date | Status | Author | Reviewer | Change | Commit |
|
|
| --- | --- | --- | --- | --- | --- |
|
|
| 2026-10-10 | Accepted | Jens Tirsvad Nielsen | S01 | Initial version | [bc3bd07] |
|
|
|
|
Allowed Status values: `Proposed`, `Accepted`, `Rejected`, `Deprecated`, `Superseded by ADR-NNNN`.
|
|
|
|
---
|
|
|
|
## Context
|
|
|
|
The project plan names reviewers by stakeholder ID: S01 (Product Owner) is
|
|
the approving reviewer, S05 (DevOps owner and security authority) owns the
|
|
milestones, and S03 operates runners and secrets. The Stakeholder Analysis
|
|
([SA-001]) says credential, token and permission design cannot be accepted
|
|
without S05, and the Business Case lists S05's review of every security-relevant
|
|
change as the mitigation for a risk. In practice S01 has been approving
|
|
documents and has stood in for S05 and S03 (the first time is recorded in
|
|
[RC-001]), because there is currently one person doing all three roles. The
|
|
framework also requires that a reviewer is not the author of an artifact.
|
|
|
|
Options:
|
|
|
|
1. **Require each named person to review.** The record is independent, but
|
|
work waits for a person who is not available in the project's current
|
|
setup, and the S05 actions in RC-001 and RC-011 stayed open.
|
|
2. **S01 approves for everyone and the records say so.** Work continues, and
|
|
each record names who really approved.
|
|
3. **Drop the other reviewers from the documents.** Simple, but it hides who
|
|
is accountable and removes the way back to independent review.
|
|
|
|
## Decision
|
|
|
|
An artifact approved by S01 counts as approved for the stakeholders named
|
|
as its reviewers or action owners (S05, S03), and the record says that S01
|
|
stood in. This applies to every artifact of this project, including the review
|
|
records themselves, until a named stakeholder asks to review in their own
|
|
right; that person's review then replaces the stand-in for later changes.
|
|
|
|
## Consequences
|
|
|
|
**Positive:**
|
|
|
|
- Work is not blocked by a reviewer who is not present, and the records stay honest about who approved.
|
|
- The way back to independent review is kept: the stakeholder IDs stay in the documents.
|
|
|
|
**Negative:**
|
|
|
|
- No independent check: the author, the approving reviewer and the stand-in are the same person, so a security-relevant change (credentials, tokens, permissions, workflow code) has had no second reader.
|
|
- It conflicts with the text of [SA-001] (S05 must accept credential, token and permission design) and with the Business Case mitigation "S05 reviews every change"; both still say so and need an amendment, or S05 needs to be told.
|
|
- The framework rule that the reviewer must not be the author is not met; this is a project deviation to be taken upstream, not a framework change.
|
|
|
|
## Affected Artifacts
|
|
|
|
- [SA-001] — the statement that credential, token and permission design cannot be accepted without S05 no longer holds.
|
|
- [RC-001] — its action item for an independent S05 review is closed by this decision; the other records that refer to it follow.
|
|
|
|
---
|
|
|
|
[SA-001]: ../stakeholder-analysis.md
|
|
[RC-001]: ../sqa/reviews/rc-001-business-case.md
|
|