Review Record: PP-001 Project Plan (MIL-008)

Metadata

Key Value
ID RC-062
CrossReference PP-001, BC-001, MIL-008

Version History

Date Status Author Reviewer Change Commit
2026-10-13 Accepted Jens Tirsvad Nielsen S01 Initial version 9aeb74e

Artifact Under Review

  • Instance reviewed: PP-001
  • Checklist used: none: the Project Plan has no QC checklist. Validated against the Business Case BC-001 and the Go / No-Go criteria of each listed milestone, as PP.md prescribes.
  • Scope: delta re-review for the added MIL-008 row, Gantt entries, Scope Coverage, Dependencies, one Plan Risk and the counts; the earlier record is RC-053
  • Language and domain: n/a (technical type)
  • Mode: supervised (the AI prepared the record; S01, the user, gave the Go in chat on 2026-10-13)

Checklist Results

# Criterion Status Evidence/Notes
1 Every milestone in the plan has a MIL-* document and the plan's dates equal that document's target date Pass MIL-001 to MIL-008 exist; the MIL-008 decision date 2026-11-15 equals its Target Date.
2 Every Business Case scope item is covered by a gateway Pass The wiki publisher shared with other repositories is covered by MIL-006 and MIL-008 (O2, O3).
3 The schedule respects the Business Case constraints Pass The Business Case sets no deadline; the MIL-008 window overlaps the October and November windows and says so under Planning Assumptions.
4 Dependencies between milestones are stated Pass MIL-006 to MIL-008 is in the Dependencies diagram and in MIL-008's own document.
5 Every gateway has an owner who is a stakeholder ID Pass MIL-008 is owned by S05.
6 Plan content is internally consistent Pass "Eight milestones", the Planning Assumptions, the Gantt entries, the Gateway Schedule and the Scope Coverage agree.
7 Open Issues are current Pass Unchanged items remain open; a plan risk was added for the repositories that still use the scoped workflow.

Overall Verdict

Go - all seven criteria pass; no findings. S01 gave the Go in chat on 2026-10-13, after the change was merged as pull request 137 with the plan row Proposed; this record and the plan row are set to Accepted in the follow-up.

Action Items

Action Owner Due
Set PP-001 and this record to Accepted (done in the follow-up that follows pull request 137) S05 2026-10-13
Review ADR-0009 (still without a review record) S01 after the plan