Files
github-action/docs/sqa/reviews/rc-076-mil-011-plan.md
T
Tirsvad 3d7a9df3a3 Review and accept MIL-011 (RC-076)
First read found three corrections: the wording of O5 in the
traceability, "ten milestones" in the plan's purpose, and a scope row that
is not a Business Case item. Go; accepted by the author as stand-in for
S01, not independent. MIL-011 and its plan row are Accepted; the
traceability matrix has the new rows.
2026-10-14 16:00:04 +08:00

4.5 KiB

Review Record: MIL-011 and PP-001 (MIL-011)

Metadata

Key Value
ID RC-076
CrossReference MIL-011, PP-001, BC-001, QC-MIL-001

Version History

Date Status Author Reviewer Change Commit
2026-10-14 Accepted Jens Tirsvad Nielsen S01 Initial version; accepted by the author in chat as stand-in for S01, after three corrections found in the first read pending

Artifact Under Review

  • Instance reviewed: MIL-011; delta of PP-001 for the added milestone
  • Checklist used: QC-MIL-001 for the milestone; for the plan, the criteria of PP.md (no QC checklist exists for PP-001)
  • Scope: full review of MIL-011; delta re-review of PP-001, earlier record RC-068
  • Language and domain: n/a (technical type)
  • Mode: supervised, not independent (the author, Jens Tirsvad Nielsen, asked in chat on 2026-10-14 for the review and the acceptance and stands in for S01; the AI prepared the evidence)

Checklist Results

# Criterion Status Evidence/Notes
1 A concrete deliverable is defined for every gate Pass ## Deliverable names the patch release 2.1.1: the defaults, the test, the guides, README and three wiki languages at @v2, the changelog entry, and the framework Badges page without the workaround.
2 Explicit Go/No-Go criteria are stated for each gate Pass Eight criteria, each with a checkable Go and No-Go: reproduction, a list per workflow, a test that fails on a seeded default, a search that finds no @v1, a run on the instance, the release level and tags, the framework page, the review record.
3 Dependencies on other milestones are explicitly mapped Pass [MIL-010] (the workflow and its guide) and ADR-0006 (the release process); in the plan's dependency diagram (MIL-010 -> MIL-011).
4 Each milestone is traceable to a Business Case objective or KPI Pass O5 of BC-001; the first read found its wording paraphrased wrongly, now quoted from the Business Case.
5 Milestone owner and approving reviewer are identified Pass Owner S05, approving reviewer S01; both are in SA-001.
6 Milestone has a defined target date consistent with project constraints Pass 2026-10-23; the Business Case sets no deadline. The date precedes the planned decision date of [MIL-010] (2027-01-30) because that milestone was released on 2026-10-14; the milestone says so and does not change the MIL-010 row.

Plan delta (PP-001)

# Criterion Status Evidence/Notes
1 Every milestone has a MIL-* document and the plan's dates equal that document's target date Pass MIL-001 to MIL-011 exist; the MIL-011 decision date (2026-10-23) equals its Target Date.
2 Every Business Case scope item is covered by a gateway Pass The first read found a scope row that is not a Business Case item; it is removed and MIL-011 is listed beside MIL-010 for the badges item.
3 The schedule respects the Business Case constraints Pass No deadline in the Business Case; the window is one week.
4 Dependencies between milestones are stated Pass MIL-003 + MIL-004 -> MIL-010 -> MIL-011.
5 Every gateway has an owner who is a stakeholder ID Pass S05.
6 Plan content is internally consistent Pass The first read found "ten milestones" in the Purpose; it is now "eleven", and the Gantt, the schedule and the dependencies agree.
7 Open Issues are current Pass No plan risk was added for a default that names an old major; the release process and the test of task 3 carry the rule. Observation, not a failure.

Overall Verdict

Go - all criteria pass after three corrections found in the first read (the O5 wording, "ten milestones", and a scope row that was not a Business Case item). The author confirmed the acceptance in chat on 2026-10-14 as stand-in for S01; this is not an independent review.

Action Items

Action Owner Due
Confirm this record by S01 when an independent reading is possible S01 2026-10-30
Task 1: reproduce the failure and list the defaults before any change to the workflows S05 2026-10-16