S01 gave the Go on the MIL-008 plan change in chat on 2026-10-13. The change was merged as pull request 137 with the plan row Proposed; this sets PP-001 and RC-062 to Accepted.
55 lines
2.8 KiB
Markdown
55 lines
2.8 KiB
Markdown
# Review Record: PP-001 Project Plan (MIL-008)
|
|
|
|
## Metadata
|
|
| Key | Value |
|
|
| --- | --- |
|
|
| ID | RC-062 |
|
|
| CrossReference | [PP-001], [BC-001], [MIL-008] |
|
|
|
|
## Version History
|
|
| Date | Status | Author | Reviewer | Change | Commit |
|
|
| --- | --- | --- | --- | --- | --- |
|
|
| 2026-10-13 | Accepted | Jens Tirsvad Nielsen | S01 | Initial version | [9aeb74e] |
|
|
|
|
---
|
|
|
|
## Artifact Under Review
|
|
|
|
- Instance reviewed: [PP-001]
|
|
- Checklist used: none: the Project Plan has no QC checklist. Validated against the Business Case [BC-001] and the Go / No-Go criteria of each listed milestone, as `PP.md` prescribes.
|
|
- Scope: delta re-review for the added MIL-008 row, Gantt entries, Scope Coverage, Dependencies, one Plan Risk and the counts; the earlier record is RC-053
|
|
- Language and domain: n/a (technical type)
|
|
- Mode: supervised (the AI prepared the record; S01, the user, gave the Go in chat on 2026-10-13)
|
|
|
|
## Checklist Results
|
|
|
|
| # | Criterion | Status | Evidence/Notes |
|
|
| --- | --- | --- | --- |
|
|
| 1 | Every milestone in the plan has a `MIL-*` document and the plan's dates equal that document's target date | Pass | MIL-001 to MIL-008 exist; the MIL-008 decision date 2026-11-15 equals its Target Date. |
|
|
| 2 | Every Business Case scope item is covered by a gateway | Pass | The wiki publisher shared with other repositories is covered by MIL-006 and MIL-008 (O2, O3). |
|
|
| 3 | The schedule respects the Business Case constraints | Pass | The Business Case sets no deadline; the MIL-008 window overlaps the October and November windows and says so under Planning Assumptions. |
|
|
| 4 | Dependencies between milestones are stated | Pass | MIL-006 to MIL-008 is in the Dependencies diagram and in MIL-008's own document. |
|
|
| 5 | Every gateway has an owner who is a stakeholder ID | Pass | MIL-008 is owned by S05. |
|
|
| 6 | Plan content is internally consistent | Pass | "Eight milestones", the Planning Assumptions, the Gantt entries, the Gateway Schedule and the Scope Coverage agree. |
|
|
| 7 | Open Issues are current | Pass | Unchanged items remain open; a plan risk was added for the repositories that still use the scoped workflow. |
|
|
|
|
## Overall Verdict
|
|
|
|
Go - all seven criteria pass; no findings. S01 gave the Go in chat on 2026-10-13, after the change was merged as pull request 137 with the plan row `Proposed`; this record and the plan row are set to `Accepted` in the follow-up.
|
|
|
|
## Action Items
|
|
|
|
| Action | Owner | Due |
|
|
| --- | --- | --- |
|
|
| Set PP-001 and this record to `Accepted` (done in the follow-up that follows pull request 137) | S05 | 2026-10-13 |
|
|
| Review ADR-0009 (still without a review record) | S01 | after the plan |
|
|
|
|
---
|
|
|
|
---
|
|
|
|
[PP-001]: ../../project-plan.md
|
|
[BC-001]: ../../business-case.md
|
|
[MIL-008]: ../../milestones/mil-008-wiki-reusable-workflow.md
|
|
[9aeb74e]: https://git.tirsystem.com/TirSystem/github-action/commit/9aeb74e8b09bb7882847e9bd5d569dbc9856fc03
|