TirSystem/github-action: Publish wiki / publish-wiki (push) Skipped
TirSystem/github-action: Sync GitHub mirror metadata / sync-metadata (push) Skipped
Validate workflows / validate (pull_request) Successful in 19s
48 lines
2.3 KiB
Markdown
48 lines
2.3 KiB
Markdown
# Review Record: PP-001 Project Plan (MIL-007)
|
|
|
|
## Metadata
|
|
| Key | Value |
|
|
| --- | --- |
|
|
| ID | RC-053 |
|
|
| CrossReference | [PP-001], [BC-001] |
|
|
|
|
## Version History
|
|
| Date | Status | Author | Reviewer | Change | Commit |
|
|
| --- | --- | --- | --- | --- | --- |
|
|
| 2026-10-11 | Accepted | Jens Tirsvad Nielsen | S01 | Initial version | [e3ad1fa] |
|
|
|
|
---
|
|
|
|
## Artifact Under Review
|
|
|
|
- Instance reviewed: [PP-001]
|
|
- Checklist used: none: the Project Plan has no QC checklist. Validated against the Business Case [BC-001] and the Go / No-Go criteria of each listed milestone, as `PP.md` prescribes.
|
|
|
|
## Checklist Results
|
|
|
|
| # | Criterion | Status | Evidence/Notes |
|
|
| --- | --- | --- | --- |
|
|
| 1 | Every milestone in the plan has a `MIL-*` document and the plan's dates equal that document's target date | Pass | MIL-001 to MIL-007 exist; the MIL-007 decision date 2027-01-16 equals its Target Date. |
|
|
| 2 | Every Business Case scope item is covered by a gateway | Pass | Quality checks for C++ and C# are mapped to MIL-007 in Scope Coverage under the quality-check scope item (O4). |
|
|
| 3 | The schedule respects the Business Case constraints | Pass | The Business Case sets no deadline; the dates are the plan's own and say so. |
|
|
| 4 | Dependencies between milestones are stated | Pass | The Dependencies diagram shows MIL-003 and MIL-004 to MIL-007, and MIL-007 lists them in its own document. |
|
|
| 5 | Every gateway has an owner who is a stakeholder ID | Pass | MIL-007 is owned by S05. |
|
|
| 6 | Plan content is internally consistent | Pass | "Seven milestones", the Planning Assumptions, the Gantt entries, the Gateway Schedule and the Scope Coverage agree. |
|
|
| 7 | Open Issues are current | Pass | Unchanged items remain open; a plan risk was added for the runner's tools. |
|
|
|
|
## Overall Verdict
|
|
|
|
Go - all seven criteria pass; no findings. S01 gave the Go in chat on 2026-10-11, standing in for the other reviewers as ADR-0002 records; there is no independent reader.
|
|
|
|
## Action Items
|
|
|
|
| Action | Owner | Due |
|
|
| --- | --- | --- |
|
|
| Add the link to the Gitea milestone of MIL-007 to the Gateway Schedule after `--apply` | S05 | 2026-10-11 |
|
|
|
|
---
|
|
|
|
[PP-001]: ../../project-plan.md
|
|
[BC-001]: ../../business-case.md
|
|
[e3ad1fa]: https://git.tirsystem.com/TirSystem/github-action/commit/e3ad1fa7e7eef57a6793a479edb41ac6fd2db688
|