Review and accept MIL-007 and the PP-001 amendment

This commit is contained in:
2026-10-11 12:21:33 +08:00
parent 8ad19fca8d
commit e3ad1fa7e7
6 changed files with 108 additions and 10 deletions
+46
View File
@@ -0,0 +1,46 @@
# Review Record: MIL-007
## Metadata
| Key | Value |
| --- | --- |
| ID | RC-052 |
| CrossReference | [MIL-007], [QC-MIL-001] |
## Version History
| Date | Status | Author | Reviewer | Change | Commit |
| --- | --- | --- | --- | --- | --- |
| 2026-10-11 | Accepted | Jens Tirsvad Nielsen | S01 | Initial version | pending |
---
## Artifact Under Review
- Instance reviewed: [MIL-007]
- Checklist used: [QC-MIL-001]
## Checklist Results
| # | Criterion | Status | Evidence/Notes |
| --- | --- | --- | --- |
| 1 | A concrete deliverable is defined for every gate | Pass | Two reusable workflows with pinned tools, guides and wiki pages in three languages, a use in another repository and a release. |
| 2 | Explicit Go/No-Go criteria are stated for each gate | Pass | Six criteria, each with a Go and a No-Go: runner verified, ADR accepted, seeded failure visible, a run in another repository, no embedded script, released. |
| 3 | Dependencies on other milestones are explicitly mapped | Pass | MIL-003 for the contract and mechanism, MIL-004 for the release; both are closed. |
| 4 | Each milestone is traceable to a Business Case objective or KPI | Pass | O4, and US-001.09 and US-001.10 which the milestone extends. |
| 5 | Milestone owner and approving reviewer are identified | Pass | Owner S05, approving reviewer S01. |
| 6 | Milestone has a defined target date consistent with project constraints | Pass | 2027-01-16, after the last decision of the plan; the Business Case sets no deadline. |
## Overall Verdict
Go - all six criteria pass; no findings. The plan-first order holds inside the milestone: the use case and stories (task 1), the runner check (task 2) and the contract ADR (task 3) come before any workflow (tasks 4 and 5). The decision between one workflow and one per language is left to the ADR and is not made here. S01 gave the Go in chat on 2026-10-11, standing in for the other reviewers as ADR-0002 records; there is no independent reader.
## Action Items
| Action | Owner | Due |
| --- | --- | --- |
| Run `sync-project.sh --apply` so that the milestone and its issues exist | S05 | 2026-10-11 |
| Decide in the ADR (task 3) one workflow or one per language, and whether C is included | S01 | before tasks 4 and 5 |
---
[MIL-007]: ../../milestones/mil-007-cpp-csharp-quality-checks.md
[QC-MIL-001]: ../../../framework/qc/qc-milestones-gateways.md
+46
View File
@@ -0,0 +1,46 @@
# Review Record: PP-001 Project Plan (MIL-007)
## Metadata
| Key | Value |
| --- | --- |
| ID | RC-053 |
| CrossReference | [PP-001], [BC-001] |
## Version History
| Date | Status | Author | Reviewer | Change | Commit |
| --- | --- | --- | --- | --- | --- |
| 2026-10-11 | Accepted | Jens Tirsvad Nielsen | S01 | Initial version | pending |
---
## Artifact Under Review
- Instance reviewed: [PP-001]
- Checklist used: none: the Project Plan has no QC checklist. Validated against the Business Case [BC-001] and the Go / No-Go criteria of each listed milestone, as `PP.md` prescribes.
## Checklist Results
| # | Criterion | Status | Evidence/Notes |
| --- | --- | --- | --- |
| 1 | Every milestone in the plan has a `MIL-*` document and the plan's dates equal that document's target date | Pass | MIL-001 to MIL-007 exist; the MIL-007 decision date 2027-01-16 equals its Target Date. |
| 2 | Every Business Case scope item is covered by a gateway | Pass | Quality checks for C++ and C# are mapped to MIL-007 in Scope Coverage under the quality-check scope item (O4). |
| 3 | The schedule respects the Business Case constraints | Pass | The Business Case sets no deadline; the dates are the plan's own and say so. |
| 4 | Dependencies between milestones are stated | Pass | The Dependencies diagram shows MIL-003 and MIL-004 to MIL-007, and MIL-007 lists them in its own document. |
| 5 | Every gateway has an owner who is a stakeholder ID | Pass | MIL-007 is owned by S05. |
| 6 | Plan content is internally consistent | Pass | "Seven milestones", the Planning Assumptions, the Gantt entries, the Gateway Schedule and the Scope Coverage agree. |
| 7 | Open Issues are current | Pass | Unchanged items remain open; a plan risk was added for the runner's tools. |
## Overall Verdict
Go - all seven criteria pass; no findings. S01 gave the Go in chat on 2026-10-11, standing in for the other reviewers as ADR-0002 records; there is no independent reader.
## Action Items
| Action | Owner | Due |
| --- | --- | --- |
| Add the link to the Gitea milestone of MIL-007 to the Gateway Schedule after `--apply` | S05 | 2026-10-11 |
---