| 1 |
Every milestone in the plan has a MIL-* document and the plan's dates equal that document's target date |
Pass |
MIL-001 to MIL-007 exist; the MIL-007 decision date 2027-01-16 equals its Target Date. |
| 2 |
Every Business Case scope item is covered by a gateway |
Pass |
Quality checks for C++ and C# are mapped to MIL-007 in Scope Coverage under the quality-check scope item (O4). |
| 3 |
The schedule respects the Business Case constraints |
Pass |
The Business Case sets no deadline; the dates are the plan's own and say so. |
| 4 |
Dependencies between milestones are stated |
Pass |
The Dependencies diagram shows MIL-003 and MIL-004 to MIL-007, and MIL-007 lists them in its own document. |
| 5 |
Every gateway has an owner who is a stakeholder ID |
Pass |
MIL-007 is owned by S05. |
| 6 |
Plan content is internally consistent |
Pass |
"Seven milestones", the Planning Assumptions, the Gantt entries, the Gateway Schedule and the Scope Coverage agree. |
| 7 |
Open Issues are current |
Pass |
Unchanged items remain open; a plan risk was added for the runner's tools. |