Files
repo-foundry/docs/project-plan.md
T
Tirsvad 5f42d660cf Plan MIL-011: release 0.3.4
Adds the milestone MIL-011 with its review RC-034 (Go), the phase in the project
plan, MIL-011 in the CrossReference of the user stories, and the rows of the
traceability matrix. The milestone and its two issues, #90 and #91, are on
Gitea.
2026-10-13 12:54:17 +08:00

7.7 KiB

Project Plan

Metadata

Key Value
ID PP-001
CrossReference BC-001, SA-001, MIL-001, MIL-002, MIL-003, MIL-004, MIL-005, MIL-006, MIL-007, MIL-008, MIL-009, MIL-010, MIL-011, US-001

Version History

Date Status Author Reviewer Change Commit
2026-10-13 Deprecated Jens Tirsvad Nielsen S02 Added phase MIL-010 (proposed dates 2026-12-28 to 2026-12-30): the wiki token is accepted in .env and the access-token guide moves to the wiki 9cca295
2026-10-13 Accepted Jens Tirsvad Nielsen S02 Added phase MIL-011 (proposed dates 2027-01-04 to 2027-01-05): release 0.3.4 pending

Purpose

Schedule the eleven phases that deliver RepoFoundry (create-project.sh and its documentation) in dependency order. The Business Case sets no deadline, so the dates below are proposals for S01 to confirm.

Planning Assumptions

  • Week 1 starts 2026-10-05; the plan ends by 2027-01-05 (the last six phases are proposed).
  • Phase length: two weeks.
  • S01 and S02 review each phase through a pull request, as described in SA-001. For now one person holds both roles.
  • The PO language is English, so no translated copies are kept.

Gateway Schedule

Gateway Document Window Decision date Owner Stories Main deliverable Milestone
Foundation MIL-001 2026-10-05 to 2026-10-16 2026-10-16 S01 US-001.01 Safe skeleton, config parsing, prompts, tests Milestone 43
Repositories and Mirror MIL-002 2026-10-19 to 2026-10-30 2026-10-30 S02 US-001.02 GitHub and Gitea repositories and the push mirror Milestone 44
Scaffold and Release MIL-003 2026-11-02 to 2026-11-13 2026-11-13 S01 US-001.03 Local project, framework, README, final review Milestone 45
Configurable Details MIL-004 2026-11-16 to 2026-11-20 2026-11-20 S01 US-001.04 Project details preset in config.env
Credentials MIL-005 2026-11-23 to 2026-11-27 2026-11-27 S01 US-001.05 Missing credentials asked; project .env
Project License MIL-006 2026-11-30 to 2026-12-04 2026-12-04 S01 US-001.06 PROJECT_LICENSE in config.env; AGPL-3.0 default only for a public GitHub project
Framework Checklists and Usage MIL-007 2026-12-07 to 2026-12-11 2026-12-11 S01 US-001.07 qc fetched with the framework; global command; README usage
Gitea Is the Only Remote MIL-008 2026-12-14 to 2026-12-18 2026-12-18 S01 US-001.03 The local project has origin only; GitHub is reached through the mirror
Framework Files Excluded from Git MIL-009 2026-12-21 to 2026-12-23 2026-12-23 S01 US-001.03 .claude, .agents and AGENTS.md excluded from git in the new project
Wiki Token and Access-Token Guide MIL-010 2026-12-28 to 2026-12-30 2026-12-30 S01 US-001.05 TOKEN_FOR_GITEA_WIKI accepted in .env; access-token guide in the wiki
Release 0.3.4 MIL-011 2027-01-04 to 2027-01-05 2027-01-05 S01 US-001 Version 0.3.4 released on Gitea with its changelog entry
@startgantt
Project starts 2026-10-05
[Foundation] starts 2026-10-05 and ends 2026-10-16
[Foundation Go/No-Go] happens 2026-10-16
[Repositories and Mirror] starts 2026-10-19 and ends 2026-10-30
[Repositories and Mirror Go/No-Go] happens 2026-10-30
[Scaffold and Release] starts 2026-11-02 and ends 2026-11-13
[Scaffold and Release Go/No-Go] happens 2026-11-13
[Configurable Details] starts 2026-11-16 and ends 2026-11-20
[Configurable Details Go/No-Go] happens 2026-11-20
[Credentials] starts 2026-11-23 and ends 2026-11-27
[Credentials Go/No-Go] happens 2026-11-27
[Project License] starts 2026-11-30 and ends 2026-12-04
[Project License Go/No-Go] happens 2026-12-04
[Framework Checklists and Usage] starts 2026-12-07 and ends 2026-12-11
[Framework Checklists and Usage Go/No-Go] happens 2026-12-11
[Gitea Is the Only Remote] starts 2026-12-14 and ends 2026-12-18
[Gitea Is the Only Remote Go/No-Go] happens 2026-12-18
[Framework Files Excluded from Git] starts 2026-12-21 and ends 2026-12-23
[Framework Files Excluded from Git Go/No-Go] happens 2026-12-23
[Wiki Token and Access-Token Guide] starts 2026-12-28 and ends 2026-12-30
[Wiki Token and Access-Token Guide Go/No-Go] happens 2026-12-30
[Release 0.3.4] starts 2027-01-04 and ends 2027-01-05
[Release 0.3.4 Go/No-Go] happens 2027-01-05
@endgantt

Scope Coverage

Business Case scope item Gateway
Safe parsing of config.env and .env, tool checks, prompts, .gitignore MIL-001
Project name check on GitHub MIL-001
Creation of both repositories and the push mirror MIL-002
Partial-failure reporting MIL-002
Local directory, remotes, framework submodule, skills, hooks, templates, plan gate MIL-003
README and SSH prerequisite documentation MIL-003
Project details set in config.env instead of asked MIL-004
Missing credentials asked; the new project's .env MIL-005
Project license set in config.env MIL-006
Framework's own submodules fetched MIL-007
README usage from the target folder and as a global command MIL-007
The local project has origin as its only remote MIL-008
.claude, .agents and AGENTS.md excluded from git in the new project MIL-009
TOKEN_FOR_GITEA_WIKI accepted in .env; access-token guide in the wiki MIL-010
Version 0.3.4 released MIL-011

Dependencies

MIL-001 → MIL-002 → MIL-003 → MIL-004 → MIL-005 → MIL-006 → MIL-007 → MIL-008 → MIL-009 → MIL-010 → MIL-011

A No-Go moves every later date by the time needed to rework the failed criteria.

Plan Risks

Risk Impact Mitigation
No disposable GitHub organization for testing Organization-owner path untested Agree the test owners before MIL-002 starts
Gitea API behaviour differs from the swagger on the live server Mirror task takes longer Test against git.tirsystem.com early in MIL-002

Open Issues

  • Decided: the proposed dates are accepted with this plan (S01 asked for its acceptance on 2026-10-05); a change needs a new Version History row.
  • Decided: origin uses HTTPS derived from GITEA_URL, unless the SSH test passed, in which case it uses SSH on port 10022.
  • Decided: use case UC-001 "Create a new project" is created, with SSD-001; tasks that implement its steps reference it.
  • Decided: S01 and S02 are both held by one person for now.
  • Open: this plan says the script does not make the first commit; confirm before MIL-003 starts.