Accept BC, SA, PP and MIL-001 after review

Review BC-001, SA-001, PP-001 and MIL-001 and record the results as
RC-001 to RC-004. All four verdicts are Go, so their Version History
rows become Accepted and the previous rows Deprecated. MIL-002 to
MIL-004 stay Proposed.

BC-001 failed criterion 1 (cost-benefit not justified as qualitative).
Add the justification and a target-completion constraint (2026-10-14)
that PP-001 and MIL-001 are checked against.

Add the Traceability Matrix (TM-001) and register RC and TM in the
artifact registry. PP has no QC checklist, so RC-003 checks the plan
against BC-001 and the milestones instead. Author and reviewer are
both S01, a deviation noted in each record.

Refs #5
This commit is contained in:
2026-10-04 23:23:12 +08:00
parent cb28865787
commit a1ff73580f
10 changed files with 349 additions and 103 deletions
+7 -2
View File
@@ -4,12 +4,13 @@
| Key | Value |
| --- | --- |
| ID | BC-001 |
| CrossReference | [SA-001], [PP-001] |
| CrossReference | [SA-001], [PP-001], [RC-001] |
## Version History
| Date | Status | Author | Reviewer | Change | Commit |
| --- | --- | --- | --- | --- | --- |
| 2026-10-04 | Proposed | Jens Tirsvad Nielsen | S01 | Initial version | [ddfe96f] |
| 2026-10-04 | Deprecated | Jens Tirsvad Nielsen | S01 | Initial version | [ddfe96f] |
| 2026-10-04 | Accepted | Jens Tirsvad Nielsen | S01 | Added target-date constraint and cost-benefit justification<br>Accepted after review RC-001 | pending |
---
@@ -99,6 +100,7 @@ Supports the author's goal of completing the 100 Days of Code bootcamp with prof
- No runtime dependencies unless needed.
- Do not commit, push or open a PR without the author's request.
- Product Owner language: English.
- Target completion 2026-10-14 (proposed by S01; no external deadline).
## Cost–Benefit Assessment
@@ -106,6 +108,8 @@ Supports the author's goal of completing the 100 Days of Code bootcamp with prof
| --- | --- |
| About one to two evenings of the author's time | A shareable, tested, documented reference solution |
The comparison is qualitative on purpose: this is a personal learning project with no revenue or budget, so a monetary ROI would be artificial. The cost is the author's time; the benefit is the shareable reference solution and practice gained.
## Stakeholders
| Stakeholder ID (SA) | Interest in this project |
@@ -123,3 +127,4 @@ Proceed — the scope is small, the risks are low and the result serves all thre
[SA-001]: ./stakeholder-analysis.md
[PP-001]: ./project-plan.md
[ddfe96f]: https://git.tirsystem.com/Tirsvad-Udemy-100_days_of_code/014-higher_lower/commit/ddfe96ffa459d5e4b2e30d71bd53878aba2cfc5d
[RC-001]: ./sqa/reviews/rc-001-business-case.md