011-black-jack/.claude/skills/artifact/references/MIL.md
T
Tirsvad 1d35410b8d Add planning baseline: BC, SA, PP and two gateways
Create the Business Case, Stakeholder Analysis (S01 course participant,
S02 Udemy coursists, S03 GitHub viewers), Project Plan and the milestone
documents MIL-001 (project setup, 6 tasks) and MIL-002 (game
implementation, 8 tasks) for the console Blackjack game.

Register PP and MIL in the artifact registry, set the PO language to en,
and link the synced Gitea milestones in the Gateway Schedule.

Refs #1
Refs #2
Refs #3
Refs #4
Refs #5
Refs #6
Refs #7
Refs #8
Refs #9
Refs #10
Refs #11
Refs #12
Refs #13
Refs #14
2026-10-04 21:38:09 +08:00

2.6 KiB

Milestone / Gateway (MIL)

Cite in CrossReference only if the instance exists (new-artifact.sh checks this for you):

  • BC — The objective / constraint (e.g. project duration) the milestone traces to
  • KPI — The KPI IDs evaluated at this gate
  • US — Forward: the user stories (US-<v>.<NN>) that deliver this gateway

Required sections (after Metadata / Version History)

  1. Purpose — what decision this gate supports.
  2. Deliverable — the concrete, tangible output evaluated (never just a date).
  3. Go / No-Go Criteria — objectively checkable, one per row.
  4. Dependencies — other milestones that must precede this one.
  5. Traceability — the Business Case objective and/or KPI ID(s) it maps to.
  6. Ownership — owner and approving reviewer as SA stakeholder IDs.
  7. Target Date — consistent with Business Case constraints.
  8. Tasks — the implementation-level breakdown for this phase, one row per task: # | Task | Summary | Needs its own Use Case/User Story? | Reference. Task is a short title (becomes the Issue title on sync); Summary is one to three sentences of real context — what the task actually involves and why, grounded in this project's own documents, not a restatement of the title — so someone reading the Issue on Gitea/GitHub understands it without opening this file (becomes the Issue body).

Breaking a phase into tasks

Not every task needs a use case — only model one when the task is something a user, or another system, actually does:

  • Needs a use case/user story — "User resets password", "Admin exports customer report", "Payment service processes refund". Set the column to Yes and put the US-…/UC-… ID in Reference.
  • Plain task, no use case — "Refactor authentication middleware", "Add database index", "Upgrade React version", "Fix null-pointer bug", "Add unit tests", "Configure CI pipeline", "Optimize SQL query". Set the column to No and leave Reference blank, or point at the design artifact it implements (DCD-…, OC-…).

The hierarchy is: Business goal → Feature/requirement → Use case/user story → Tasks. The use case explains why a feature exists; tasks explain how the team implements it — most tasks stay at that level.

Syncing to Gitea/GitHub

Each MIL-* gateway becomes one Milestone on the git host; its ## Tasks row become Issues assigned to that milestone. Use the project-planning skill and framework/scripts/sync-project.sh — do not create these by hand.